A team uses Kanban and notices the 'In Progress' column frequently has 8 items when the WIP limit is 5. What should the team do?
-
A
Increase the WIP limit to match actual usage
-
B
Stop pulling new work and swarm to finish in-progress items
-
C
Remove the WIP limits as they are impractical
-
D
Split the In Progress column into sub-stages