A Scrum team consistently fails to complete all Sprint backlog items by the end of the Sprint. What is the BEST first step to address this?
-
A
Extend the Sprint length to allow more time
-
B
Review and improve the team's estimation practices
-
C
Remove team members who are underperforming
-
D
Add more items to the next Sprint to increase motivation