A team's cumulative flow diagram shows bands widening in the 'In Progress' stage over three sprints. What does this most likely indicate?
-
A
Work is completing faster than it enters
-
B
Work-in-progress limits are being violated or work is piling up
-
C
The team is delivering at a sustainable pace
-
D
Backlog refinement is improving