In Kanban, what is the primary purpose of setting Work In Progress (WIP) limits?
-
A
To restrict the number of team members on a project
-
B
To prevent overloading the system and expose bottlenecks
-
C
To limit the number of customers who can submit requests
-
D
To cap the total number of stories in the backlog