What is the primary distinction between 'verification' and 'validation' in the context of technical acceptance?
-
A
Verification checks cost; validation checks schedule
-
B
Verification confirms the product was built correctly per specifications; validation confirms the right product was built for its intended use
-
C
Verification is performed by the contractor; validation is always performed by the customer
-
D
Verification and validation are interchangeable terms in acceptance inspection