What does the Critical Path Method (CPM) identify in a project schedule?
-
A
The longest sequence of dependent activities that determines project duration
-
B
The most expensive sequence of activities in the project
-
C
The sequence of activities with the most available float
-
D
The activities that require the most labor resources