What is the difference between verification and validation in acceptance testing?
-
A
Verification confirms the product was built correctly per specifications; validation confirms it meets user needs
-
B
Verification is performed by the customer; validation is performed by the supplier
-
C
Verification checks packaging; validation checks labeling
-
D
Verification is a final inspection; validation is an initial inspection