What is the primary purpose of a 'value engineering' study in construction?
-
A
To achieve required functions at the lowest overall cost without sacrificing quality
-
B
To increase the aesthetic value of a building design
-
C
To appraise the market value of completed construction
-
D
To evaluate contractor bids for the best value