BCM Cheat Sheet 2026
The 30 highest-yield BCM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here โ free, no sign-up.
200 questions
240 min time limit
70.00% to pass
- The statute of limitations in construction defect claims refers to: โ The time period within which a legal claim must be filed after discovery of a defect
- Pick the false statement. โ None of the above
- Which dispute resolution method is generally faster and less expensive than litigation in construction disputes? โ Arbitration
- What are any project's three main parts? โ Time, Budget, Quality
- As a guarantee of the tender, or ___, the contractor is obliged to deposit a certain sum with the department when submitting a bid. โ Earnest money
- The Project Management Body of Knowledge (PMBOK) identifies how many primary process groups? โ 5
- What does 'Total Float' represent in Critical Path Method (CPM) scheduling? โ The amount of time an activity can be delayed without delaying the project completion
- A Notice to Proceed (NTP) in construction contracts signals: โ The official authorization for the contractor to begin work on a specific date
- The water-cement ratio (w/c ratio) in concrete mix design primarily affects: โ Compressive strength and durability of the hardened concrete
- Tensile strength is a structural weakness of concrete, which is why: โ Steel reinforcing bars (rebar) are embedded in concrete to resist tension forces
- Project closeout in construction typically includes all of the following EXCEPT: โ Issuing the original project charter
- A differing site condition (Type I) claim arises when: โ Actual site conditions materially differ from what was indicated in the contract documents
- Which type of respiratory protection provides the highest level of protection against airborne contaminants? โ Self-Contained Breathing Apparatus (SCBA)
- CMU stands for which common masonry construction material? โ Concrete Masonry Unit
- Substantial completion in construction law is typically defined as the point when: โ The project is sufficiently complete for the owner to use it for its intended purpose
- A subcontractor's 'pay-when-paid' clause in a construction contract means: โ The GC is not obligated to pay the sub until the GC receives payment from the owner
- A conceptual (order-of-magnitude) estimate in construction typically has an accuracy range of: โ -30% to +50%
- The minimum distance construction workers must maintain from energized overhead power lines when using equipment (without special precautions) is: โ 10 feet for lines up to 50 kV
- In construction cost control, a 'cost code' system is used to: โ Organize and track actual expenditures by work category for comparison to the estimate
- Which document formally establishes the approved project schedule that is used to measure and report schedule performance? โ Schedule Baseline
- The Estimate at Completion (EAC) in EVM, assuming future performance matches current CPI, is calculated as: โ Budget at Completion รท CPI
- In construction scheduling, a lag is best defined as: โ A delay intentionally added between the start or finish of two activities
- Choose the untrue statement from the list below: โ None of these
- A Schedule of Values (SOV) in construction is used primarily to: โ Break down the contract sum by work items to support monthly payment applications
- A construction project's baseline schedule is best described as: โ The approved, original project schedule used as a reference for performance measurement
- Fast-tracking as a schedule compression technique involves: โ Overlapping phases or activities that were originally planned in sequence
- Which risk response strategy involves transferring the financial consequences of a risk to a third party, such as through insurance? โ Transfer
- The OSHA 'Fatal Four' in construction refers to the four leading causes of worker fatalities, which are: โ Falls, struck-by, caught-in/between, and electrocution
- Higher volume, lower cost commodities need: โ Little Inspection
- Which type of logical relationship in Precedence Diagramming means 'Activity B cannot start until Activity A finishes'? โ Finish-to-Start (FS)
Turn these facts into recall: