The Program Evaluation and Review Technique (PERT) differs from CPM primarily because PERT:
-
A
Does not use a network diagram
-
B
Uses three time estimates to account for schedule uncertainty
-
C
Only works for repetitive construction tasks
-
D
Requires resource loading for every activity