Agile Project Management Flashcards
7 cards from real AZ-400 practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Agile Project Management flashcards as text
A team's lead time has been increasing over several sprints. Which Azure Boards tool best helps them diagnose where delays are accumulating in their workflow?
Answer: Cumulative Flow Diagram
The Cumulative Flow Diagram reveals where work is piling up by showing the width of each workflow band widening, indicating a bottleneck stage.
In Azure Boards, what is the function of 'Area Paths' in an Agile project setup?
Answer: Organize work items by team, product area, or functional group
Area Paths create a hierarchical grouping structure that allows teams or product areas to own and filter their own work items within a shared project.
Which practice in Agile and DevOps involves team members describing completed work and demonstrating it to stakeholders at the end of a sprint?
Answer: Sprint Review
The Sprint Review is a collaborative event where the team demonstrates completed work to stakeholders and gathers feedback to inform the backlog.
A DevOps team wants to link Azure Boards work items directly to commits and pull requests to maintain traceability. What must developers do when committing code?
Answer: Reference the work item ID using # notation in the commit message or PR description
Prefixing or referencing work item IDs with # in commit messages or PR descriptions automatically links the commit to the corresponding Azure Boards item.
What is the primary benefit of 'backlog refinement' (formerly grooming) sessions in an Agile team using Azure DevOps?
Answer: Ensuring backlog items are well-defined, estimated, and prioritized before sprint planning
Backlog refinement ensures stories are ready for sprint planning by adding detail, estimating effort, and ranking them appropriately.
When a team uses 'story points' for estimation in Azure Boards, what characteristic makes them more useful than hour-based estimates?
Answer: They are relative and account for complexity and uncertainty rather than exact time
Story points are relative measures of effort, complexity, and risk, making them more stable than hour estimates which vary by individual and context.
In Azure DevOps, a team wants to prevent a work item from being moved to 'Active' unless it has an assigned owner. How is this enforced?
Answer: Configuring work item rules in the inherited process to require a field value on state transition
Work item rules in the inherited process model can require specific fields (like Assigned To) to be filled in before a state transition is allowed.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- home.pearsonvue.com — Test delivery · verified Nov 2026
- learn.microsoft.com — Passing score, score validity, eligibility, fees, renewal, score release, exam format, time limit, retake fee, retake policy · verified Oct 2026