A new industrial facility near a Class I area (national park) triggers PSD review. Which additional analysis is required?
-
A
An Air Quality Related Values (AQRV) analysis in coordination with the Federal Land Manager
-
B
A full environmental impact statement under NEPA filed with Congress
-
C
An offset purchase equal to 200% of the projected emission increase
-
D
A groundwater contamination study submitted to the EPA