During sprint planning, a sales stakeholder demands a feature be added that was not in the sprint backlog. The BEST response is to:
-
A
Add the feature immediately to avoid damaging the relationship
-
B
Capture the request, evaluate priority against the backlog, and communicate the decision transparently
-
C
Refuse all mid-sprint additions as a firm policy
-
D
Let the development team decide whether to accept it