During planning poker, two team members give estimates of 3 and 13 for the same story. What is the BEST next step?
-
A
Average the two estimates and move on
-
B
Use the lower estimate to maintain velocity
-
C
Have both members explain their reasoning to align understanding
-
D
Ask the Product Owner to decide the correct estimate