A development team consistently overestimates velocity, leading to incomplete sprints. What is the BEST corrective action?
-
A
Increase sprint length to accommodate more work
-
B
Use yesterday's weather by averaging the last 3-5 sprints
-
C
Have the Product Owner reduce story point values
-
D
Add more developers to the team immediately