A Product Owner wants to change the Sprint Goal midway through a Sprint. What should the Scrum Master do?
-
A
Allow the change if the team agrees
-
B
Coach the Product Owner that the Sprint Goal should not change during a Sprint
-
C
Cancel the Sprint immediately
-
D
Call an emergency Sprint Planning session