During a Sprint Review, the Scrum Team discovers that a stakeholder's key requirement was misunderstood. What is the BEST next step?
-
A
Cancel the Sprint and restart planning
-
B
Add the clarified requirement to the Product Backlog for prioritization
-
C
Extend the Sprint to address the misunderstood requirement
-
D
Assign blame to the Product Owner for the miscommunication