A team's velocity has been inconsistent for the past 6 sprints. What is the BEST way to use this data for sprint planning?
-
A
Use the highest velocity sprint as the target
-
B
Use the average velocity over the last 3-6 sprints
-
C
Ignore velocity and use team member estimates only
-
D
Use the lowest velocity sprint to be conservative