A Scrum team consistently fails to complete all sprint backlog items by the end of the sprint. According to Scrum, what is the MOST appropriate response?
-
A
Extend the sprint until all items are complete
-
B
Move incomplete items back to the Product Backlog and re-prioritize with the Product Owner
-
C
Reduce the team's velocity target for future sprints automatically
-
D
Ask the Scrum Master to assign tasks more evenly among team members