In SAFe (Scaled Agile Framework), what is the primary purpose of the Program Increment (PI) Planning event?
-
A
To review completed work and update the backlog
-
B
To align multiple Agile teams around a shared mission and objectives for the next 8-12 weeks
-
C
To conduct retrospectives across all teams simultaneously
-
D
To assign individual tasks to developers for the upcoming sprint