Which capacity planning technique operates at the most detailed level, considering individual machines and operators?
-
A
Resource Requirements Planning (RRP)
-
B
Rough-Cut Capacity Planning (RCCP)
-
C
Capacity Requirements Planning (CRP)
-
D
Input/Output Control