APICS APICS Master Scheduling & Capacity Planning 2 — Questions and Answers
Question 1: Which capacity planning technique operates at the most detailed level, considering individual machines and operators?
- Resource Requirements Planning (RRP)
- Rough-Cut Capacity Planning (RCCP)
- Capacity Requirements Planning (CRP) (Correct answer)
- Input/Output Control
Correct answer: Capacity Requirements Planning (CRP)
CRP uses MRP-generated planned and released orders to calculate detailed load at each work center and machine.
Question 2: A 'load profile' in capacity planning represents:
- The number of workers per shift
- The standard hours of work required over time for a given item (Correct answer)
- The machine downtime schedule
- The inventory carrying cost curve
Correct answer: The standard hours of work required over time for a given item
A load profile shows the pattern of capacity requirements over time needed to manufacture an item through its routing.
Question 3: What does 'demonstrated capacity' refer to in production planning?
- The theoretical maximum output of a machine
- The actual output achieved historically by a work center (Correct answer)
- The capacity after adding overtime
- The budgeted production level
Correct answer: The actual output achieved historically by a work center
Demonstrated capacity is based on actual historical output data, reflecting real-world performance rather than theoretical limits.
Question 4: In the context of master scheduling, 'nervousness' refers to:
- Worker stress during high-demand periods
- Frequent and unnecessary changes to planned orders (Correct answer)
- Volatile customer demand signals
- Uncertainty in supplier lead times
Correct answer: Frequent and unnecessary changes to planned orders
MRP nervousness occurs when small changes in demand cause large, cascading changes throughout the planned order schedule.
Question 5: Which scheduling approach assigns jobs to work centers based on the least amount of work remaining?
- First-In-First-Out (FIFO)
- Shortest Processing Time (SPT)
- Least Work Remaining (LWR) (Correct answer)
- Critical Ratio (CR)
Correct answer: Least Work Remaining (LWR)
The Least Work Remaining (LWR) rule prioritizes jobs with the fewest remaining operations or least remaining processing time.
Question 6: The 'critical ratio' dispatching rule calculates priority as:
- Processing time divided by due date
- (Time remaining until due date) divided by (work remaining) (Correct answer)
- Order quantity divided by lead time
- Safety stock divided by demand rate
Correct answer: (Time remaining until due date) divided by (work remaining)
A critical ratio below 1.0 indicates the job is behind schedule, while above 1.0 means it has slack time available.
Which capacity planning technique operates at the most detailed level, considering individual machines and operators?