Read the first 7 Safety Protocols & Compliance flashcards as text
On construction sites, 120-volt, single-phase, 15- and 20-amp receptacle outlets that are not part of permanent wiring must be protected by GFCIs or by what alternative?
Answer: An assured equipment grounding conductor program
1926.404(b)(1) allows either GFCIs or an assured equipment grounding conductor program for temporary wiring.
Under OSHA Subpart CC, what minimum clearance must a crane maintain from power lines rated up to 350 kV when using the simplified approach?
Answer: 20 feet
1926.1408 Option 2 requires a 20-foot minimum clearance for lines up to 350 kV.
Which OSHA subpart governs permit-required confined spaces specifically in construction?
Answer: Subpart AA
Subpart AA (1926.1200–1213) covers confined spaces in construction, effective 2015.
According to the hierarchy of hazard controls, which control method is considered most effective?
Answer: Elimination
Elimination physically removes the hazard and sits at the top of the NIOSH hierarchy of controls.
What is the primary purpose of a lockout/tagout procedure during equipment maintenance?
Answer: To prevent unexpected energization or release of stored energy while workers service equipment
Lockout/tagout isolates hazardous energy so machinery cannot start or release energy during servicing.
Head protection used on construction sites must meet which consensus standard as referenced by OSHA?
Answer: ANSI Z89.1
1926.100 references ANSI Z89.1 for protective helmets.
Under OSHA construction noise rules (1926.52), what is the permissible exposure limit for an 8-hour time-weighted average?
Answer: 90 dBA
Table D-2 of 1926.52 sets the 8-hour PEL at 90 dBA.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026