A curtain wall system has a 20-week fabrication lead time after shop drawing approval. What should the constructor do first to protect the schedule?
Answer: Prioritize and expedite the shop drawing submittal and review cycle
Long-lead items depend on approved submittals, so speeding up the submittal and review cycle protects the delivery date.
Resource leveling within available float typically results in which outcome?
Answer: Peaks and valleys in resource demand are smoothed without extending the project
Leveling moves non-critical activities within their float to smooth resource use while keeping the completion date.
A takeoff shows 10,000 SF of drywall, and the estimator uses a 10% waste factor. How much drywall should be ordered?
Answer: 11,000 SF
10,000 SF × 1.10 = 11,000 SF to cover cutting and breakage waste.
Which document lets a supplier show how a specific product meets the specification before installation?
Answer: Product data submittal
Product data submittals give manufacturer information so the design team can confirm the product complies with the specifications.
Just-in-time (JIT) delivery is most helpful on which kind of project?
Answer: A congested urban site with little storage space
JIT cuts the need for on-site storage, which matters most on tight urban sites.
A resource histogram is used primarily to:
Answer: Display resource demand over time
A histogram plots how many units of a resource (such as workers) are needed in each time period.
Which cost is classified as an ownership cost rather than an operating cost for construction equipment?
Answer: Depreciation
Depreciation, interest, insurance, and taxes are ownership costs that accrue whether or not the equipment runs.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026