← All AIC Flashcard Decks

Contract Administration Flashcards

7 cards from real AIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Contract Administration flashcards as text
  1. Delays caused by the owner and by the contractor overlap on the critical path. What is the most common result?

    Answer: The contractor gets a time extension but no delay damages

    For concurrent delay, courts usually grant time but deny compensation, because neither party can recover for the overlap.

  2. A contractor claims lost labor productivity. Which method compares productivity in an unimpacted period with productivity in an impacted period?

    Answer: Measured mile analysis

    Measured mile analysis compares unimpacted and impacted periods on the same project to isolate the productivity loss.

  3. Which AIA document does the contractor submit at final payment to certify that its debts and claims have been paid?

    Answer: G706

    G706 is the Contractor's Affidavit of Payment of Debts and Claims, used at closeout.

  4. Which lien waiver takes effect only after the payment it covers actually clears?

    Answer: Conditional waiver

    A conditional waiver depends on receipt of payment, which protects the claimant if the payment fails.

  5. A cost-plus contract has an allowance for owner-selected light fixtures, and the actual cost differs from the allowance. How is the contract sum adjusted?

    Answer: By change order for the difference

    A201 §3.8 requires a Change Order to adjust the Contract Sum for the difference between the allowance and actual cost.

  6. What generally marks Substantial Completion?

    Answer: The owner can occupy or use the work for its intended purpose

    Substantial Completion is the stage when the work is complete enough for the owner to use it as intended; punch list items may still remain.

  7. The contractor's request for payment includes materials stored off site. What do owners typically require before paying for them?

    Answer: Approval in advance, proof of insurance, and documented transfer of title to the owner

    Owners usually require advance approval, insurance, and title transfer before paying for off-site stored materials.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026