← All AIC Flashcard Decks

Contract Administration Flashcards

7 cards from real AIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Contract Administration flashcards as text
  1. A clause sets $2,000 per day for late completion. When will a court most likely refuse to enforce it?

    Answer: When the amount is a penalty rather than a reasonable pre-estimate of damages

    Courts enforce liquidated damages that reasonably estimate hard-to-calculate damages, but reject amounts that act as penalties.

  2. Which type of delay usually entitles a contractor to a time extension but no additional money?

    Answer: Unusually severe weather

    Severe weather is generally an excusable but non-compensable delay.

  3. Under AIA A201, how long is the standard correction period after Substantial Completion?

    Answer: One year

    A201 §12.2.2 sets a one-year correction period starting at Substantial Completion.

  4. Under the federal Miller Act, which bonds must a prime contractor provide on qualifying federal construction contracts?

    Answer: Performance bond and payment bond

    The Miller Act requires performance and payment bonds on federal construction contracts above the statutory threshold.

  5. A second-tier supplier with no direct contract with the prime contractor wants to claim on a Miller Act payment bond. What notice must it give?

    Answer: Written notice to the prime contractor within 90 days of last furnishing labor or material

    Second-tier claimants must give written notice to the prime contractor within 90 days of the last furnishing.

  6. What is the primary purpose of AIA G703?

    Answer: Listing schedule-of-values line items and progress for a payment application

    G703 is the continuation sheet to the G702 payment application; it details each schedule-of-values line.

  7. Which clause makes the owner's payment to the general contractor a condition precedent to the GC paying its subcontractor?

    Answer: Pay-if-paid

    A pay-if-paid clause shifts the risk of owner nonpayment to the subcontractor; a pay-when-paid clause only sets timing.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026