Contract Administration Flashcards
7 cards from real AIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Contract Administration flashcards as text
Under AIA A201-2017, within how many days after the event giving rise to a claim must the claimant generally initiate the claim?
Answer: 21 days
A201-2017 §15.1.3 requires Claims to be initiated within 21 days after the occurrence of the event or after the claimant first recognizes the condition.
Which AIA document lets the owner and architect direct a change in the work before the contractor agrees on price or time adjustments?
Answer: G714 Construction Change Directive
A Construction Change Directive (G714) orders changed work without the contractor's prior agreement on cost or time.
A contractor finds concealed subsurface rock that the contract documents did not show. Under A201, what must the contractor do first?
Answer: Promptly notify the owner and architect before disturbing the conditions
A201 §3.7.4 requires notice before the conditions are disturbed, and no later than 14 days after first observing them.
What does the Spearin doctrine establish?
Answer: The owner impliedly warrants that the plans and specifications it furnishes are adequate
United States v. Spearin (1918) holds that an owner who supplies design specifications impliedly warrants that they are adequate.
An owner-caused delay extends the project, and the contractor wants home office overhead it could not absorb. Which method is commonly used to calculate it?
Answer: Eichleay formula
The Eichleay formula allocates unabsorbed home office overhead to the days of compensable owner-caused delay.
Which statement about shop drawings under AIA A201 is correct?
Answer: They are not contract documents
A201 §3.12.4 says shop drawings, product data, and samples are not Contract Documents; they show how the contractor intends to meet the design.
Under AIA A201, a contractor has not been paid within 7 days of the payment due date through no fault of its own. What may it do next?
Answer: Stop work after an additional 7 days' written notice to the owner and architect
A201 §9.7 lets the contractor stop work after giving 7 additional days' written notice.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026