Construction Project Planning Flashcards
7 cards from real AIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Construction Project Planning flashcards as text
In a risk register, a risk with a 20% probability and a $150,000 impact has an expected monetary value of:
Answer: $30,000
EMV = probability x impact = 0.20 x $150,000 = $30,000.
Purchasing builder's risk insurance to cover potential fire damage during construction is an example of which risk response?
Answer: Transfer
Insurance shifts the financial consequence of a risk to a third party, which is risk transfer.
Which activity relationship is rarest in construction scheduling and generally discouraged?
Answer: Start-to-Finish
Start-to-Finish relationships are counterintuitive and rarely appropriate, so most scheduling specifications discourage them.
When multiple paths have zero total float, the project is said to have:
Answer: Multiple critical paths, increasing schedule risk
Several zero-float paths mean delays on any of them delay completion, increasing overall schedule risk.
Which project delivery method allows a construction manager to provide preconstruction planning services and then hold trade contracts with a guaranteed maximum price?
Answer: Construction Manager at Risk
CM at Risk provides preconstruction input and then assumes delivery risk under a GMP.
An activity's duration is calculated as 2,400 SF of formwork at a crew productivity of 300 SF per day. What is the duration?
Answer: 8 days
Duration = quantity / productivity rate = 2,400 / 300 = 8 days.
Which of the following best describes a schedule 'milestone' activity?
Answer: A zero-duration event marking a significant point
Milestones have zero duration and mark key events like substantial completion or dry-in.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026