Construction Project Planning Flashcards
7 cards from real AIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Construction Project Planning flashcards as text
An approved schedule used as the reference point for measuring progress and analyzing delays is the:
Answer: Baseline schedule
The baseline is the approved original plan against which actual progress and delays are measured.
Which constraint type, if overused in a CPM schedule, most distorts float calculations and logic?
Answer: Hard date constraints such as Must Start On
Hard date constraints override network logic and can create false float or negative float, masking true critical paths.
An activity is shown with negative total float. What does this indicate?
Answer: The current plan cannot meet a constrained or required finish date
Negative float means the network cannot meet an imposed date without recovery actions.
Constructability review during preconstruction is primarily intended to:
Answer: Identify design issues that affect ease, cost, and sequence of building
Constructability reviews use construction knowledge to improve buildability, sequencing, and cost before work starts.
A site logistics plan typically addresses all of the following EXCEPT:
Answer: Subcontractor payment retainage percentages
Retainage is a contract and payment term, not a physical site logistics element.
Which document lists each required shop drawing and product submittal along with due dates and review durations?
Answer: Submittal register/schedule
The submittal register tracks required submittals, responsible parties, and dates so procurement stays on schedule.
A cost-loaded schedule is most useful for which purpose?
Answer: Producing a projected cash flow (S-curve)
Assigning costs to activities lets planners forecast cash flow over time, typically shown as an S-curve.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026