  1. A project has a planned value of $500,000, earned value of $450,000, and actual cost of $480,000. What is the Schedule Performance Index (SPI)?

    Answer: 0.90

    SPI = EV / PV = 450,000 / 500,000 = 0.90, meaning the project is behind schedule.

  2. Using the same data (PV $500,000, EV $450,000, AC $480,000), what is the Cost Variance?

    Answer: -$30,000

    CV = EV - AC = 450,000 - 480,000 = -$30,000, indicating a cost overrun.

  3. What is the primary purpose of resource leveling in a construction schedule?

    Answer: To smooth resource demand peaks, possibly extending duration

    Resource leveling adjusts activity timing to reduce peaks and valleys in resource usage, which may extend the schedule.

  4. Which scheduling method is best suited for repetitive linear work such as high-rise floors or highway segments?

    Answer: Line of Balance

    Line of Balance (linear scheduling) shows production rates of repetitive units and helps keep crews flowing continuously.

  5. In PERT, an activity has optimistic 4 days, most likely 6 days, and pessimistic 14 days. What is its expected duration?

    Answer: 7 days

    Te = (O + 4M + P) / 6 = (4 + 24 + 14) / 6 = 7 days.

  6. A three-week look-ahead schedule is primarily used by the field team to:

    Answer: Plan short-term work, crews, and constraints in detail

    Look-ahead schedules break near-term work into detail so superintendents can coordinate crews, materials, and constraints.

  7. Which item is typically identified early in planning as a long-lead procurement item?

    Answer: Switchgear and custom electrical equipment

    Switchgear and other custom fabricated equipment often take months to fabricate, so they must be released early.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026