  1. In a CPM network, an activity has ES=10, EF=15, LS=14, and LF=19. What is its total float?

    Answer: 4 days

    Total float equals LS minus ES (or LF minus EF), which is 14 - 10 = 4 days.

  2. Free float for an activity is best defined as the time it can be delayed without delaying:

    Answer: The early start of any immediate successor

    Free float is the delay an activity can absorb without pushing back the early start of any succeeding activity.

  3. Which precedence diagramming relationship is most commonly used to model overlapping work such as starting drywall a few days after framing begins?

    Answer: Start-to-Start with a lag

    A Start-to-Start relationship with lag lets a successor begin a set time after the predecessor starts, modeling overlap.

  4. A scheduler shortens the project by adding a second crew to critical activities at extra cost. This technique is called:

    Answer: Crashing

    Crashing compresses the schedule by adding resources to critical activities, typically increasing direct cost.

  5. When crashing a schedule, which activity should normally be shortened first?

    Answer: The critical activity with the lowest cost slope

    The most economical approach crashes the critical activity with the lowest cost per day saved first.

  6. Which risk is most closely associated with fast-tracking a design-bid-build project?

    Answer: Rework caused by starting work before design is complete

    Fast-tracking overlaps phases, so construction may begin on incomplete design, increasing rework risk.

  7. The lowest level of a Work Breakdown Structure, where cost and schedule are estimated and controlled, is called a:

    Answer: Work package

    Work packages are the lowest WBS deliverable level used to estimate, schedule, and assign responsibility.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026