AIC Construction Scheduling & Time Management Flashcards
6 cards from real AIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 AIC Construction Scheduling & Time Management flashcards as text
Which scheduling method uses a network diagram to identify the longest path through a project?
Answer: Critical Path Method (CPM)
CPM identifies the critical path — the longest sequence of dependent tasks — to determine the minimum project duration.
In CPM scheduling, 'float' (or slack) refers to:
Answer: The amount of time an activity can be delayed without affecting the project finish date
Float is the amount of time a non-critical activity can be delayed without delaying the overall project completion.
A project has a Planned Value (PV) of $500,000 and an Earned Value (EV) of $450,000. What does this indicate?
Answer: The project is behind schedule
When EV is less than PV, the Schedule Variance is negative, indicating the project is behind schedule.
Which scheduling technique is best suited for repetitive construction tasks such as highway paving?
Answer: Line of Balance
Line of Balance is designed for repetitive work, showing production rates and crew continuity across multiple identical units.
What is the primary purpose of a look-ahead schedule in construction project management?
Answer: To provide a detailed 3–6 week rolling plan for near-term work execution
Look-ahead schedules focus on the near-term work window, helping superintendents coordinate resources, materials, and subcontractors for upcoming tasks.
In PERT (Program Evaluation and Review Technique), the expected duration of an activity is calculated as:
Answer: (Optimistic + 4×Most Likely + Pessimistic) / 6
PERT uses a weighted average formula — (O + 4M + P) / 6 — giving the most weight to the most likely estimate.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026