  1. Under the AIC Body of Knowledge, which document formally establishes the project baseline schedule?

    Answer: The schedule approved by the owner and incorporated into the contract

    The baseline schedule is the owner-approved, contract-incorporated schedule against which all progress and changes are measured.

  2. A contractor receives a change order that adds 30 days to the project duration. What schedule document should be formally updated?

    Answer: The baseline schedule via a time impact analysis

    Contract time changes require a formal time impact analysis and revision to the baseline schedule to reflect the updated project duration.

  3. Which scheduling software is most commonly used on large US commercial construction projects?

    Answer: Primavera P6

    Primavera P6 is the industry-standard CPM scheduling software widely required by owners and GCs on large commercial and infrastructure projects.

  4. What is the purpose of a Time Impact Analysis (TIA) in construction scheduling?

    Answer: To quantify how a change event affects the project completion date

    A TIA inserts a change event into the schedule at the time it occurred to demonstrate its impact on the critical path and project completion date.

  5. When a construction activity has Total Float = 0, it means:

    Answer: Any delay to that activity will delay the project completion date

    Zero total float identifies a critical activity — any delay to it directly extends the overall project finish date.

  6. Which scheduling technique incorporates probability distributions to account for uncertainty in activity durations?

    Answer: PERT / Monte Carlo simulation

    PERT and Monte Carlo simulation use statistical distributions of activity durations to estimate the probability of meeting a given project completion date.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. aic-builds.org — Test delivery, late registration, test dates, renewal, eligibility, fees, exam format, time limit, exam information · verified Oct 2026