Associate Constructor (AC) Exam — Questions and Answers
Question 1: Which equipment cost usually rises as the machine gets older?
- Repair and maintenance costs (Correct answer)
- Interest on the purchase price
- Annual depreciation under straight-line
- Initial purchase price
Correct answer: Repair and maintenance costs
Repair and maintenance costs generally climb as equipment ages, which drives replacement decisions.
Question 2: A crane's rated load capacity typically decreases when:
- The load is lifted slowly
- Outriggers are fully extended
- The load radius increases (Correct answer)
- The boom angle increases
Correct answer: The load radius increases
Crane capacity drops as the radius from the center of rotation to the load grows.
Question 3: An owner disputes a pay application line item. What is the best first step?
- File a mechanic's lien the same day
- Stop work immediately
- Remove the line item without discussion
- Meet to review backup documentation and the schedule of values (Correct answer)
Correct answer: Meet to review backup documentation and the schedule of values
Reviewing supporting documentation resolves most payment disagreements at the lowest level.
Question 4: Which factor has the greatest impact on fluctuating construction material costs?
- Supervisor experience
- Weather conditions
- Project location signage
- Market conditions (Correct answer)
Correct answer: Market conditions
Market conditions, including supply and demand, economic trends, and global events, have the greatest impact on fluctuating construction material costs. Factors like raw material availability, transportation costs, trade policies, and overall economic health directly influence pricing. These external forces can cause significant and rapid changes in material expenses, impacting project budgets.
Question 5: Which IBC construction type allows exterior walls of noncombustible materials while interior building elements may be of any material permitted by code?
- Type II
- Type IV
- Type V
- Type III (Correct answer)
Correct answer: Type III
Type III construction requires noncombustible (or fire-retardant-treated wood) exterior walls, while interior elements may be any permitted material.
Question 6: Which surety bond guarantees the owner that the contractor will complete the work according to the contract terms?
- Bid bond
- Payment bond
- Performance bond (Correct answer)
- License bond
Correct answer: Performance bond
A performance bond protects the owner if the contractor defaults on completing the contracted work.
Question 7: Under the straight-line method, a $200,000 loader with a $20,000 salvage value and a 6-year life depreciates how much per year?
- $36,667
- $33,333
- $30,000 (Correct answer)
- $20,000
Correct answer: $30,000
($200,000 − $20,000) ÷ 6 = $30,000 per year.
Question 8: In multistory concrete construction, what is reshoring?
- Adding shores to the formwork before concrete placement
- Placing shores under a slab after the original forms and shores have been removed (Correct answer)
- Removing all shores at once after 28 days
- Bracing excavation walls with timber
Correct answer: Placing shores under a slab after the original forms and shores have been removed
Reshores are placed after stripping to support young slabs and spread construction loads to the floors below.
Question 9: When a construction activity has Total Float = 0, it means:
- Resources have been fully allocated to that activity
- The activity has been completed
- Any delay to that activity will delay the project completion date (Correct answer)
- The activity can be rescheduled freely
Correct answer: Any delay to that activity will delay the project completion date
Zero total float identifies a critical activity — any delay to it directly extends the overall project finish date.
Question 10: Under OSHA, how far back from the edge of an excavation must spoil piles and equipment be kept, at minimum?
- 5 feet
- 2 feet (Correct answer)
- 10 feet
- 1 foot
Correct answer: 2 feet
OSHA 1926.651(j)(2) requires materials and equipment to be at least 2 feet from the excavation edge.
Question 11: An owner lets non-critical light fixtures operate until they fail, then replaces them. This is best described as:
- Run-to-failure (corrective) maintenance (Correct answer)
- Reliability-centered maintenance
- Predictive maintenance
- Proactive maintenance
Correct answer: Run-to-failure (corrective) maintenance
Run-to-failure is a deliberate corrective strategy for low-cost, non-critical items where failure has little consequence.
Question 12: A wellpoint system on a construction site is used to do what?
- Monitor settlement of adjacent buildings
- Test pile capacity
- Inject grout to stabilize soils
- Lower the groundwater table to allow dry excavation (Correct answer)
Correct answer: Lower the groundwater table to allow dry excavation
Wellpoints are closely spaced small wells connected to a header and pump that draw down groundwater.
Question 13: Under OSHA 1926.453, what fall protection is required for workers in a boom-supported aerial lift?
- A body belt or harness with lanyard attached to the boom or basket (Correct answer)
- None if the guardrails are intact
- A safety net below the work area
- A lanyard tied to an adjacent structure
Correct answer: A body belt or harness with lanyard attached to the boom or basket
Workers in boom lifts must wear fall protection with the lanyard attached to the boom or basket, never to a nearby structure.
Question 14: Under the AIC's ethical standards, how should a constructor handle confidential project information obtained from a previous client?
- Disclose it only to competitors who are bidding on similar work
- Share it with the new client if it would benefit the current project
- Use it freely if the previous contract has ended
- Keep it strictly confidential and never use it to the detriment of the former client (Correct answer)
Correct answer: Keep it strictly confidential and never use it to the detriment of the former client
Constructors are ethically obligated to maintain confidentiality of client information indefinitely, not just during the project.
Question 15: A trench planned to be 22 feet deep requires a protective system designed by whom?
- A registered professional engineer (Correct answer)
- The competent person on site
- The superintendent
- The OSHA area director
Correct answer: A registered professional engineer
Protective systems for excavations deeper than 20 feet must be designed by a registered professional engineer.
Question 16: Which international standard specifies requirements for a quality management system that construction firms may be certified to?
- ISO 31000
- ISO 14001
- ISO 9001 (Correct answer)
- ISO 45001
Correct answer: ISO 9001
ISO 9001 is the quality management system standard; 14001 is environmental and 45001 is safety.
Question 17: An activity's duration is calculated as 2,400 SF of formwork at a crew productivity of 300 SF per day. What is the duration?
- 6 days
- 12 days
- 8 days (Correct answer)
- 7 days
Correct answer: 8 days
Duration = quantity / productivity rate = 2,400 / 300 = 8 days.
Question 18: Under OSHA Subpart R (Steel Erection), the general fall protection trigger height for workers other than connectors and deckers in a CDZ is:
- 30 feet
- 10 feet
- 6 feet
- 15 feet (Correct answer)
Correct answer: 15 feet
Steel erection workers must be protected from falls of more than 15 feet above a lower level.
Question 19: A load chart rating is based on outriggers being fully extended. What should the crew do if the outriggers can only be partly extended?
- Use the load chart for that specific outrigger position, if the manufacturer provides one (Correct answer)
- Proceed if the ground is firm
- Add counterweight beyond the manufacturer's limit
- Use the full-extension chart with a 10% reduction
Correct answer: Use the load chart for that specific outrigger position, if the manufacturer provides one
Capacity must come from the manufacturer's chart for the actual outrigger configuration.
Question 20: Which activity relationship is rarest in construction scheduling and generally discouraged?
- Start-to-Start
- Finish-to-Start
- Finish-to-Finish
- Start-to-Finish (Correct answer)
Correct answer: Start-to-Finish
Start-to-Finish relationships are counterintuitive and rarely appropriate, so most scheduling specifications discourage them.
Question 21: A general contractor wants coverage under a subcontractor's commercial general liability policy for claims arising from the sub's work. What should the GC require?
- A builder's risk policy
- A payment bond
- A certificate of occupancy
- An additional insured endorsement (Correct answer)
Correct answer: An additional insured endorsement
An additional insured endorsement extends the sub's CGL coverage to protect the GC for liability arising from the sub's operations.
Question 22: A subcontractor offers a project manager tickets to a major sporting event during contract negotiations. Under ethical guidelines, the project manager should:
- Decline the gift to avoid any appearance of impropriety (Correct answer)
- Accept the tickets if their value is below $100
- Accept but disclose the gift to senior management only after award
- Accept the tickets as a routine business courtesy
Correct answer: Decline the gift to avoid any appearance of impropriety
Ethical guidelines require constructors to avoid gifts or gratuities that could influence, or appear to influence, procurement decisions.
Question 23: In tilt-up construction, how are the wall panels typically produced?
- Precast at an off-site plant and trucked in
- Cast horizontally on the floor slab or a casting bed, then lifted into place by crane (Correct answer)
- Cast vertically in gang forms
- Slipformed continuously in place
Correct answer: Cast horizontally on the floor slab or a casting bed, then lifted into place by crane
Tilt-up panels are cast flat on site, usually on the building slab, then tilted up with a crane.
Question 24: OSHA defines a 'competent person' as someone who can identify existing and predictable hazards and also has what?
- An OSHA 500 trainer card
- At least 10 years of field experience
- A college degree in safety
- Authority to take prompt corrective measures to eliminate them (Correct answer)
Correct answer: Authority to take prompt corrective measures to eliminate them
A competent person must both recognize hazards and have the authority to take prompt corrective action.
Question 25: Material laydown areas should be planned mainly to:
- Maximize the distance from the work
- Avoid being shown on the site logistics plan
- Put all materials at the site entrance
- Minimize double-handling and keep materials close to where they will be installed (Correct answer)
Correct answer: Minimize double-handling and keep materials close to where they will be installed
Good laydown planning cuts rehandling and travel time while staying clear of work areas and access routes.
Question 26: Under the IBC, a high-rise building is one with an occupied floor located more than how far above the lowest level of fire department vehicle access?
- 55 feet
- 120 feet
- 75 feet (Correct answer)
- 100 feet
Correct answer: 75 feet
The IBC defines a high-rise as having an occupied floor more than 75 feet above the lowest level of fire department vehicle access.
Question 27: Which machine works best for excavating soft, wet material below grade at a long reach, such as dredging a canal?
- Dragline (Correct answer)
- Skid-steer loader
- Front shovel
- Bulldozer
Correct answer: Dragline
A dragline casts its bucket far out and drags it back, which suits wet material at long reach.
Question 28: A GA-214 Level 5 gypsum board finish is distinguished by what?
- Texture spray only
- A thin skim coat of joint compound over the entire surface (Correct answer)
- Tape embedded only, no coating
- No joint treatment at all
Correct answer: A thin skim coat of joint compound over the entire surface
Level 5 adds a skim coat over the whole surface for walls with critical lighting or gloss paint.
Question 29: Under OSHA crane rules, how often must a competent person visually inspect wire rope in active use?
- Each shift (Correct answer)
- Monthly
- Weekly
- Annually
Correct answer: Each shift
OSHA 1926.1413 requires a visual inspection of wire rope by a competent person every shift.
Question 30: A stored-materials payment request for items held off site usually requires:
- Proof of insurance, title transfer documentation, and owner approval (Correct answer)
- Nothing beyond an invoice
- Verbal confirmation from the supplier
- Delivery to the owner's home office
Correct answer: Proof of insurance, title transfer documentation, and owner approval
Owners usually require bills of sale, insurance, and sometimes inspection before paying for materials stored off site.
Question 31: What does a transmittal accomplish when sending documents to the owner?
- It records what was sent, to whom, when, and for what purpose (Correct answer)
- It serves as a change order
- It replaces the submittal log
- It approves the documents
Correct answer: It records what was sent, to whom, when, and for what purpose
Transmittals provide a documented chain of custody for project communications.
Question 32: White powdery deposits appear on a brick wall after heavy rains. What should the first maintenance step be?
- Find and stop the source of water moving through the masonry (Correct answer)
- Sandblast the entire wall
- Apply a waterproof paint immediately
- Replace all affected brick
Correct answer: Find and stop the source of water moving through the masonry
Efflorescence comes from water carrying soluble salts to the surface, so controlling the moisture source comes first.
Question 33: What is the primary purpose of a Job Hazard Analysis (JHA)?
- To schedule project deadlines.
- To conduct employee performance reviews.
- To determine employee salaries.
- To identify potential job hazards and implement controls. (Correct answer)
Correct answer: To identify potential job hazards and implement controls.
A Job Hazard Analysis (JHA) is a systematic process used to identify potential hazards associated with each step of a specific job or task. Once identified, the JHA then outlines the necessary control measures to eliminate or reduce these risks to an acceptable level. This proactive approach is crucial for preventing accidents and ensuring worker safety on construction sites.
Question 34: A public owner terminates a contract for convenience. What can the contractor typically recover?
- Cost of work performed plus reasonable overhead and profit on that work (Correct answer)
- Anticipated profit on the entire contract
- Nothing beyond retainage
- Liquidated damages from the owner
Correct answer: Cost of work performed plus reasonable overhead and profit on that work
A termination-for-convenience recovery covers work performed and wind-down costs, not lost profit on unperformed work.
Question 35: In a risk register, a risk with a 20% probability and a $150,000 impact has an expected monetary value of:
- $30,000 (Correct answer)
- $120,000
- $15,000
- $150,000
Correct answer: $30,000
EMV = probability x impact = 0.20 x $150,000 = $30,000.
Question 36: A site logistics plan typically addresses all of the following EXCEPT:
- Material laydown and staging areas
- Temporary access roads and gates
- Subcontractor payment retainage percentages (Correct answer)
- Crane locations and swing radius
Correct answer: Subcontractor payment retainage percentages
Retainage is a contract and payment term, not a physical site logistics element.
Question 37: A continuous footing is 2 ft wide, 1 ft deep, and 150 LF long. What is its concrete volume?
- 22.2 CY
- 33.3 CY
- 11.1 CY (Correct answer)
- 5.6 CY
Correct answer: 11.1 CY
2 x 1 x 150 = 300 CF, and 300 / 27 = 11.1 CY.
Question 38: How does a direct tension indicator (DTI) washer show adequate bolt pretension?
- A spline twists off the bolt end
- Its protrusions compress until the gap is reduced to a specified feeler-gage refusal (Correct answer)
- It changes color when heated
- It produces an audible click
Correct answer: Its protrusions compress until the gap is reduced to a specified feeler-gage refusal
DTI protrusions flatten under bolt tension, and installers check the remaining gap with a feeler gage.
Question 39: The principle of 'fairness to competitors' in construction ethics primarily requires that constructors:
- Compete on the basis of merit and refrain from false or misleading statements about competitors (Correct answer)
- Avoid bidding in markets where a competitor has an established presence
- Share project estimates with competitors to ensure fair pricing
- Match competitors' bids within 5% to promote market stability
Correct answer: Compete on the basis of merit and refrain from false or misleading statements about competitors
Ethical competition requires relying on one's own qualifications and merits while refraining from disparaging or misrepresenting competitors.
Question 40: Which element is CRITICAL for maintaining proficiency in tools & equipment operation within American Institute of Constructors?
- Performing techniques only when absolutely necessary
- Regular practice with ongoing professional development and skill updates (Correct answer)
- Learning from informal sources without verification
- Initial certification alone without continuing education
Correct answer: Regular practice with ongoing professional development and skill updates
Maintaining proficiency requires regular practice combined with ongoing professional development to stay current with evolving best practices.
Question 41: Which document lets a supplier show how a specific product meets the specification before installation?
- Daily report
- Certificate of substantial completion
- Change order
- Product data submittal (Correct answer)
Correct answer: Product data submittal
Product data submittals give manufacturer information so the design team can confirm the product complies with the specifications.
Question 42: Which change can the architect order without changing the contract sum or time under A201?
- A minor change in the work (Correct answer)
- A value engineering proposal
- A Change Order
- A Construction Change Directive
Correct answer: A minor change in the work
Section 7.4 lets the architect order minor changes consistent with the design intent without adjusting sum or time.
Question 43: What is the ethical obligation of a constructor who discovers that a competitor obtained a contract through bribery of a public official?
- Inform only the project owner and take no further action
- Ignore it to avoid involvement in a competitor's affairs
- Use the information to renegotiate their own contract terms
- Report the misconduct to the appropriate authorities (Correct answer)
Correct answer: Report the misconduct to the appropriate authorities
Ethical professional practice requires constructors to report known illegal conduct, including bribery, to the appropriate authorities.
Question 44: Which repair method is most appropriate for restoring structural integrity to a dormant (non-moving) crack in a concrete beam?
- Epoxy injection (Correct answer)
- Applying a cementitious surface coating
- Routing and sealing with polyurethane sealant
- Dry-packing with sand
Correct answer: Epoxy injection
Epoxy injection bonds the crack faces of dormant cracks and restores structural continuity.
Question 45: What is a critical path in a construction schedule?
- The sequence of least important activities.
- The budget summary.
- The longest sequence determining project duration. (Correct answer)
- A list of required safety checks.
Correct answer: The longest sequence determining project duration.
In a construction schedule, the critical path is the longest sequence of activities that must be completed on time for the entire project to finish by its deadline. Any delay in an activity on the critical path will directly delay the project's overall completion. Identifying and managing the critical path is essential for effective project control and ensuring timely delivery.
Question 46: In a life-cycle cost analysis, what is the present value of a $10,000 replacement cost occurring in 5 years at a 6% discount rate?
- $8,396
- $13,382
- $7,000
- $7,473 (Correct answer)
Correct answer: $7,473
PV = $10,000 / 1.06^5 = $10,000 / 1.3382 = $7,473.
Question 47: An anchorage for a personal fall arrest system, when not designed by a qualified person, must support at least how much per employee attached?
- 10,000 pounds
- 5,000 pounds (Correct answer)
- 3,000 pounds
- 1,800 pounds
Correct answer: 5,000 pounds
1926.502(d)(15) requires anchorages to support 5,000 pounds per employee or maintain a safety factor of two under a qualified person's supervision.
Question 48: In trench excavations 4 feet or more deep, a stairway, ladder, or ramp must be located so lateral travel to it is no more than:
- 35 feet
- 25 feet (Correct answer)
- 15 feet
- 50 feet
Correct answer: 25 feet
1926.651(c)(2) requires a means of egress within 25 feet of lateral travel for workers in trenches 4 feet or deeper.
Question 49: Which of the following best describes 'fee splitting' and why it is considered unethical in construction?
- Paying undisclosed referral fees to secure work, which creates hidden conflicts of interest (Correct answer)
- Dividing a contract fee among multiple partners, which reduces transparency
- Sharing profit with subcontractors, which undermines competitive bidding
- Charging different clients different rates for the same service
Correct answer: Paying undisclosed referral fees to secure work, which creates hidden conflicts of interest
Undisclosed fee splitting creates hidden conflicts of interest and violates the principle of transparency owed to clients.
Question 50: In construction professional practice, 'bid shopping' after award is generally considered unethical because it:
- Increases project cost by creating additional administrative burden
- Undermines subcontractor trust and the integrity of the competitive bidding process (Correct answer)
- Is prohibited by the AIC certification agreement
- Violates federal procurement regulations in all jurisdictions
Correct answer: Undermines subcontractor trust and the integrity of the competitive bidding process
Bid shopping after award breaks the implicit trust of the competitive process and discourages subcontractors from submitting their best prices.
Question 51: In construction workforce management, 'manpower loading' refers to:
- The ratio of skilled to unskilled labor on the crew
- The maximum weight a worker can carry on site
- Plotting the number of workers required over the project timeline to match schedule demands (Correct answer)
- Calculating total labor cost as a percentage of the bid
Correct answer: Plotting the number of workers required over the project timeline to match schedule demands
Manpower loading charts show how many workers are needed in each time period, helping managers plan hiring, layoffs, and resource allocation.
Question 52: How should unexpected results during tools & equipment operation be handled in American Institute of Constructors?
- Ignore results that do not match expectations
- Attribute unexpected results to equipment error automatically
- Document the findings, analyze potential causes, and consult protocols (Correct answer)
- Repeat the procedure until desired results are achieved
Correct answer: Document the findings, analyze potential causes, and consult protocols
Documenting unexpected findings, analyzing causes, and consulting established protocols ensures proper investigation and appropriate response.
Question 53: A project has an earned value (EV) of $400,000 and an actual cost (AC) of $500,000. What is the Cost Performance Index and what does it show?
- 1.25; behind schedule
- 1.25; under budget
- 0.80; ahead of schedule
- 0.80; over budget (Correct answer)
Correct answer: 0.80; over budget
CPI = EV / AC = 400,000 / 500,000 = 0.80, and a CPI below 1.0 means the project is over budget.
Question 54: What is a lien waiver used for in contract administration?
- To confirm payment and waive future claims (Correct answer)
- To file RFIs
- To track jobsite safety
- To issue change orders
Correct answer: To confirm payment and waive future claims
A lien waiver is a crucial document in construction contract administration used to confirm that a party, such as a subcontractor or supplier, has received payment for their work or materials. By signing it, they legally waive their right to file a mechanics lien against the property for that specific payment amount. This protects the property owner and general contractor from future claims and ensures clear title.
Question 55: What is the main purpose of a Computerized Maintenance Management System (CMMS)?
- Producing the construction schedule's critical path
- Tracking work orders, asset histories, and preventive maintenance schedules (Correct answer)
- Bidding maintenance subcontracts publicly
- Calculating structural loads for repairs
Correct answer: Tracking work orders, asset histories, and preventive maintenance schedules
A CMMS holds asset records, creates and tracks work orders, and automates PM scheduling.
Question 56: Under IBC Chapter 33, when must a standpipe used during construction be in place in a building that requires standpipes?
- Only after the permanent fire pump is commissioned
- Before the building is enclosed
- Before construction exceeds 40 feet above the lowest level of fire department vehicle access (Correct answer)
- Before the certificate of occupancy is issued
Correct answer: Before construction exceeds 40 feet above the lowest level of fire department vehicle access
IBC 3311.1 requires at least one standpipe for construction use before the building exceeds 40 feet above the lowest fire department access level.
Question 57: Which of the following best defines 'conflict of interest' in construction professional practice?
- A scheduling conflict between two concurrent projects
- Disagreement between the owner and the design team
- A dispute between two subcontractors on a project
- A situation where a constructor's personal interests could improperly influence professional judgment (Correct answer)
Correct answer: A situation where a constructor's personal interests could improperly influence professional judgment
A conflict of interest occurs when a constructor has personal, financial, or other interests that could compromise or appear to compromise their professional judgment.
Question 58: A subcontract clause requiring the sub to defend and hold the general contractor harmless from claims arising from the sub's work is called what?
- Force majeure clause
- No-damages-for-delay clause
- Liquidated damages clause
- Indemnification clause (Correct answer)
Correct answer: Indemnification clause
An indemnification (hold harmless) clause shifts liability for certain losses from one party to another.
Question 59: Which statement about shop drawings under AIA A201 is correct?
- They are not contract documents (Correct answer)
- They become contract documents once approved
- Only the owner can approve them
- They override the specifications when they conflict
Correct answer: They are not contract documents
A201 §3.12.4 says shop drawings, product data, and samples are not Contract Documents; they show how the contractor intends to meet the design.
Question 60: An owner makes a contractor meet the original deadline despite excusable delays, and refuses to grant time extensions. What may the contractor claim?
- Constructive acceleration (Correct answer)
- Accord and satisfaction
- Cardinal change
- Termination for default
Correct answer: Constructive acceleration
Constructive acceleration occurs when the owner forces faster work by denying time extensions the contractor is entitled to.
Question 61: What is the primary purpose of a pre-task plan (PTP) in construction workforce management?
- To identify hazards and assign controls before crew members begin a specific work task (Correct answer)
- To update the master schedule with daily production data
- To document worker wages for payroll processing
- To record punch-in and punch-out times for all workers
Correct answer: To identify hazards and assign controls before crew members begin a specific work task
Pre-task plans require crew members to identify job-specific hazards and controls before starting work, promoting hazard awareness and accountability.
Question 62: Under OSHA construction noise rules (1926.52), what is the permissible exposure limit for an 8-hour time-weighted average?
- 80 dBA
- 85 dBA
- 90 dBA (Correct answer)
- 95 dBA
Correct answer: 90 dBA
Table D-2 of 1926.52 sets the 8-hour PEL at 90 dBA.
Question 63: AIC members are expected to pursue continuing education primarily because:
- It generates networking opportunities that lead to new contracts
- Ongoing learning maintains the competence necessary to serve clients and the public responsibly (Correct answer)
- It is the only way to maintain state contractor licensing
- It is required by federal law for all contractors
Correct answer: Ongoing learning maintains the competence necessary to serve clients and the public responsibly
The AIC expects members to pursue continuing education to maintain and expand the competence required to practice responsibly and ethically.
Question 64: In American Institute of Constructors, how should materials & resource management challenges be prioritized?
- By the preferences of senior management
- Based on potential impact, urgency, and alignment with strategic objectives (Correct answer)
- Based solely on cost considerations
- In the order they were identified
Correct answer: Based on potential impact, urgency, and alignment with strategic objectives
Prioritizing based on impact, urgency, and strategic alignment ensures resources are directed where they will produce the greatest benefit.
Question 65: A contractor claims lost labor productivity. Which method compares productivity in an unimpacted period with productivity in an impacted period?
- Eichleay formula
- Critical path method
- Measured mile analysis (Correct answer)
- Total cost method
Correct answer: Measured mile analysis
Measured mile analysis compares unimpacted and impacted periods on the same project to isolate the productivity loss.
Question 66: What is the MOST important skill for effective materials & resource management in American Institute of Constructors?
- Maintaining strict authority over all decisions
- Clear communication and the ability to align team efforts with objectives (Correct answer)
- Technical expertise alone without people skills
- Avoiding conflict at all costs
Correct answer: Clear communication and the ability to align team efforts with objectives
Clear communication is essential for aligning team efforts, building consensus, and ensuring everyone understands and works toward shared objectives.
Question 67: What is the primary purpose of a lockout/tagout procedure during equipment maintenance?
- To document equipment repair history for warranties
- To prevent unexpected energization or release of stored energy while workers service equipment (Correct answer)
- To restrict unauthorized operators from using equipment during the shift
- To satisfy insurance requirements for equipment rental
Correct answer: To prevent unexpected energization or release of stored energy while workers service equipment
Lockout/tagout isolates hazardous energy so machinery cannot start or release energy during servicing.
Question 68: According to the AIC Code of Ethics, what is a constructor's primary professional obligation when a conflict arises between client interests and public safety?
- Follow whichever course minimizes project delays
- Defer to the project engineer's judgment
- Prioritize the client's financial interests
- Prioritize public safety above client interests (Correct answer)
Correct answer: Prioritize public safety above client interests
The AIC Code of Ethics mandates that constructors place public safety, health, and welfare above all other considerations, including client interests.
Question 69: A hidden defect that a reasonable inspection at turnover could not have found is called a:
- Punch-list item
- Change directive
- Latent defect (Correct answer)
- Patent defect
Correct answer: Latent defect
Latent defects are concealed defects, and they are often subject to longer statutes of limitation or repose.
Question 70: An estimate that prices complete building components, such as an exterior wall per SF including studs, sheathing, insulation, and finish, is called a(n):
- Square-foot estimate
- Order-of-magnitude estimate
- Detailed unit-price estimate
- Assemblies (systems) estimate (Correct answer)
Correct answer: Assemblies (systems) estimate
Assemblies estimates group related items into systems and are commonly used during design development.
Question 71: Which type of delay usually entitles a contractor to a time extension but no additional money?
- Late owner-furnished equipment
- Owner-caused design error
- Unusually severe weather (Correct answer)
- Owner-ordered suspension of work
Correct answer: Unusually severe weather
Severe weather is generally an excusable but non-compensable delay.
Question 72: In CSI MasterFormat (2004 and later editions), Division 31 covers:
- Plumbing
- Electrical
- Earthwork (Correct answer)
- Finishes
Correct answer: Earthwork
Division 31 is Earthwork, while Electrical is 26, Plumbing is 22, and Finishes is 09.
Question 73: An owner orders changes so extensive that the project is fundamentally different from what was bargained for. What is this called?
- Constructive change
- Minor change
- Cardinal change (Correct answer)
- Deductive change
Correct answer: Cardinal change
A cardinal change goes beyond the scope of the original contract and can be treated as a breach.
Question 74: In PERT (Program Evaluation and Review Technique), the expected duration of an activity is calculated as:
- (Optimistic + 4×Most Likely + Pessimistic) / 6 (Correct answer)
- (Most Likely + Pessimistic) / 2
- Pessimistic - Optimistic
- (Optimistic + Most Likely + Pessimistic) / 3
Correct answer: (Optimistic + 4×Most Likely + Pessimistic) / 6
PERT uses a weighted average formula — (O + 4M + P) / 6 — giving the most weight to the most likely estimate.
Question 75: In the context of construction professional ethics, 'whistleblowing' is considered justified when:
- Internal reporting has failed to correct illegal or seriously unethical conduct that threatens public safety (Correct answer)
- A competitor consistently underbids your firm on public projects
- A subcontractor is performing slower than their schedule commitments
- A client refuses to approve a legitimate change order request
Correct answer: Internal reporting has failed to correct illegal or seriously unethical conduct that threatens public safety
External whistleblowing is ethically justified when internal reporting mechanisms have failed to address illegal or seriously unethical conduct that poses a threat to public safety.
Question 76: Under OSHA 1926.302(e), who may operate a powder-actuated fastening tool?
- Any worker wearing safety glasses
- Only the site superintendent
- Any journeyman carpenter
- Only employees trained in its operation (Correct answer)
Correct answer: Only employees trained in its operation
OSHA allows only trained employees to operate powder-actuated tools.
Question 77: A crew of 4 installs 800 LF of pipe in 5 eight-hour days. What is the productivity rate in LF per labor-hour?
- 2.5 LF/labor-hour
- 5.0 LF/labor-hour (Correct answer)
- 20 LF/labor-hour
- 40 LF/labor-hour
Correct answer: 5.0 LF/labor-hour
4 workers × 40 hours = 160 labor-hours; 800 ÷ 160 = 5.0 LF per labor-hour.
Question 78: A cost-loaded schedule is most useful for which purpose?
- Developing safety orientation content
- Tracking RFIs
- Producing a projected cash flow (S-curve) (Correct answer)
- Determining crane capacity
Correct answer: Producing a projected cash flow (S-curve)
Assigning costs to activities lets planners forecast cash flow over time, typically shown as an S-curve.
Question 79: Which compaction equipment is best suited to cohesive clay soils?
- Smooth steel-drum vibratory roller
- Sheepsfoot (padfoot) roller (Correct answer)
- Pneumatic-tired roller on sand
- Vibratory plate compactor
Correct answer: Sheepsfoot (padfoot) roller
Sheepsfoot rollers knead and compact cohesive soils from the bottom of the lift upward.
Question 80: What is the PRIMARY benefit of continuous improvement in materials & resource management for American Institute of Constructors?
- Enhanced efficiency, quality, and competitive advantage over time (Correct answer)
- Increased complexity in operations
- Reduced need for employee input
- Higher operational costs in the short term
Correct answer: Enhanced efficiency, quality, and competitive advantage over time
Continuous improvement systematically enhances efficiency and quality, leading to sustained competitive advantage.
Question 81: What is typically added to a construction estimate to account for unforeseen costs?
- Profit margin
- Labor surcharge
- Owner’s fee
- Contingency (Correct answer)
Correct answer: Contingency
A contingency is a specific amount of money added to a construction estimate to cover unforeseen costs, risks, or scope changes that may arise during the project. It acts as a buffer against unexpected events like design errors, material price fluctuations, or difficult site conditions. Including a contingency helps ensure the project remains financially viable even when facing uncertainties.
Question 82: In a CPM network, an activity has ES=10, EF=15, LS=14, and LF=19. What is its total float?
- 4 days (Correct answer)
- 9 days
- 0 days
- 5 days
Correct answer: 4 days
Total float equals LS minus ES (or LF minus EF), which is 14 - 10 = 4 days.
Question 83: In American Institute of Constructors, what role does employee training play in safety protocols & compliance?
- It is optional and only for new employees
- It primarily serves as a legal formality
- It ensures all personnel can recognize, report, and respond to hazards (Correct answer)
- It is only needed after an incident occurs
Correct answer: It ensures all personnel can recognize, report, and respond to hazards
Training empowers all personnel to recognize hazards, follow proper procedures, and respond effectively, making it a cornerstone of any safety program.
Question 84: Which field device is commonly used to quickly measure in-place density and moisture of compacted fill?
- Schmidt rebound hammer
- Slump cone
- Ultrasonic thickness gauge
- Nuclear density gauge (Correct answer)
Correct answer: Nuclear density gauge
A nuclear density gauge gives rapid in-place density and moisture readings for compaction testing.
Question 85: In cost-of-quality analysis, field inspection and material testing are classified as which cost category?
- Internal failure costs
- External failure costs
- Appraisal costs (Correct answer)
- Prevention costs
Correct answer: Appraisal costs
Appraisal costs are spent measuring and evaluating work to verify it conforms to requirements.
Question 86: Under the IBC, a college classroom building is generally classified as which occupancy group?
- Group I-4
- Group B (Correct answer)
- Group E
- Group A-3
Correct answer: Group B
Group E covers education through the 12th grade; education above 12th grade is classified as Group B.
Question 87: What is the maximum allowable slope (H:V) for a simple sloped excavation less than 20 feet deep in Type C soil?
- 3/4:1
- 2:1
- 1½:1 (Correct answer)
- 1:1
Correct answer: 1½:1
Appendix B of Subpart P limits Type C soil slopes to 1½:1 (about 34 degrees).
Question 88: Under OSHA Subpart L, fall protection is required for employees on a scaffold more than how many feet above a lower level?
- 4 feet
- 10 feet (Correct answer)
- 15 feet
- 6 feet
Correct answer: 10 feet
Scaffold users require fall protection when working more than 10 feet above a lower level.
Question 89: Which communication approach best manages client expectations when a schedule delay becomes likely?
- Let the subcontractor inform the owner
- Give early written notice with the cause, impact, and recovery options (Correct answer)
- Mention it informally at the final walkthrough
- Wait until the delay is certain before saying anything
Correct answer: Give early written notice with the cause, impact, and recovery options
Early, transparent notice with options preserves trust and contractual rights.
Question 90: Which document typically defines the project's scope, objectives, and key deliverables?
- Resource Plan
- Project Schedule
- Project Charter (Correct answer)
- Work Breakdown Structure (WBS)
Correct answer: Project Charter
The Project Charter is a foundational document that formally authorizes a project and provides a high-level overview. It typically defines the project's scope, objectives, key deliverables, stakeholders, and overall success criteria. This document serves as an agreement among stakeholders, establishing the project's purpose and boundaries.
Question 91: Under OSHA regulations, who is responsible for ensuring subcontractor employees comply with site safety rules on a multi-employer construction site?
- Only OSHA compliance officers
- Only the subcontractor that employs the workers
- The general contractor as the controlling employer, as well as each creating/exposing employer (Correct answer)
- The project owner exclusively
Correct answer: The general contractor as the controlling employer, as well as each creating/exposing employer
OSHA's multi-employer citation policy holds the general contractor (controlling employer) and creating/exposing employers responsible for hazard compliance.
Question 92: As a rule of thumb, how much grade resistance does each 1% of adverse grade add for a haul unit?
- 40 lb per ton of gross weight
- 100 lb per ton of gross weight
- 10 lb per ton of gross weight
- 20 lb per ton of gross weight (Correct answer)
Correct answer: 20 lb per ton of gross weight
Each 1% of uphill grade adds about 20 lb of resistance per ton of gross vehicle weight.
Question 93: What is the most effective method of controlling a hazard according to the hierarchy of controls?
- Engineering controls
- Hazard elimination (Correct answer)
- Use of personal protective equipment (PPE)
- Administrative controls
Correct answer: Hazard elimination
According to the hierarchy of controls, hazard elimination is the most effective method for controlling hazards because it completely removes the hazard from the workplace. If a hazard cannot be eliminated, the next most effective methods are substitution, engineering controls, administrative controls, and finally, personal protective equipment (PPE). Eliminating the hazard prevents exposure entirely.
Question 94: What does the AIC's concept of 'stewardship' in professional practice primarily refer to?
- Maintaining accurate project documentation for audit purposes
- Responsible use of resources, including financial, human, and environmental resources (Correct answer)
- Managing the owner's budget with strict cost controls
- Delegating tasks appropriately to qualified subcontractors
Correct answer: Responsible use of resources, including financial, human, and environmental resources
Stewardship in AIC professional practice encompasses responsible management of all resources — financial, human, material, and environmental — entrusted to the constructor.
Question 95: When materials are delivered, what should the receiving person check first?
- The invoice payment terms
- The supplier's credit rating
- The quantity and condition against the packing slip and purchase order (Correct answer)
- The manufacturer's stock price
Correct answer: The quantity and condition against the packing slip and purchase order
Comparing deliveries to the packing slip and PO catches shortages, wrong items, and damage right away.
Question 96: What is the function of bentonite slurry when excavating a slurry (diaphragm) wall trench?
- To waterproof the finished wall
- To hold the trench walls stable by hydrostatic pressure until concrete is tremied in (Correct answer)
- To accelerate concrete set
- To lubricate the clamshell bucket
Correct answer: To hold the trench walls stable by hydrostatic pressure until concrete is tremied in
Slurry pressure and the filter cake it forms support the trench sides until tremie concrete displaces the slurry.
Question 97: Under the AIC Body of Knowledge, which document formally establishes the project baseline schedule?
- The bid schedule submitted at tender
- The schedule approved by the owner and incorporated into the contract (Correct answer)
- The subcontractor's 2-week look-ahead
- The contractor's internal Gantt chart
Correct answer: The schedule approved by the owner and incorporated into the contract
The baseline schedule is the owner-approved, contract-incorporated schedule against which all progress and changes are measured.
Question 98: Craft labor productivity in construction is BEST measured by:
- The number of overtime hours worked
- Actual units of work installed per labor-hour compared to the estimate (Correct answer)
- Total wages paid compared to the project budget
- The number of workers on site each day
Correct answer: Actual units of work installed per labor-hour compared to the estimate
Productivity is measured by comparing actual labor-hours per unit of work installed to the estimated standard, revealing efficiency gains or losses.
Question 99: Which statement best distinguishes quality assurance (QA) from quality control (QC) on a construction project?
- QA focuses on planned processes that prevent defects, while QC inspects and tests the work to detect defects (Correct answer)
- QA and QC are identical terms used interchangeably in all contracts
- QA is performed only by the owner, while QC is performed only by the architect
- QA applies only to materials, while QC applies only to labor
Correct answer: QA focuses on planned processes that prevent defects, while QC inspects and tests the work to detect defects
QA is process-oriented and preventive, while QC is product-oriented verification through inspection and testing.
Question 100: Under OSHA 29 CFR 1926.501, at what height must construction workers on walking/working surfaces with unprotected edges be protected from falls?
- 4 feet
- 6 feet (Correct answer)
- 10 feet
- 15 feet
Correct answer: 6 feet
OSHA construction standards require fall protection at 6 feet or more above a lower level.
Question 101: Which document lets the owner direct a change in the work before the owner and contractor agree on cost or time adjustment?
- Request for Information
- Change Order
- Architect's Supplemental Instructions
- Construction Change Directive (Correct answer)
Correct answer: Construction Change Directive
A Construction Change Directive (AIA G714) orders the change when agreement on adjustment has not yet been reached.
Question 102: The AIC defines 'professional competence' in construction as requiring:
- Holding a bachelor's degree in construction management
- Passing the AIC certification exam once and maintaining membership
- Maintaining the skills and knowledge necessary to perform contracted services at an acceptable standard (Correct answer)
- Completing at least 500 hours of field work annually
Correct answer: Maintaining the skills and knowledge necessary to perform contracted services at an acceptable standard
Professional competence requires ongoing maintenance of the skills, knowledge, and judgment necessary to deliver construction services to an acceptable standard.
Question 103: Which element is CRITICAL for maintaining proficiency in installation techniques & methods within American Institute of Constructors?
- Initial certification alone without continuing education
- Learning from informal sources without verification
- Performing techniques only when absolutely necessary
- Regular practice with ongoing professional development and skill updates (Correct answer)
Correct answer: Regular practice with ongoing professional development and skill updates
Maintaining proficiency requires regular practice combined with ongoing professional development to stay current with evolving best practices.
Question 104: How does the turn-of-nut method pretension high-strength bolts?
- By shearing off a spline at the bolt tip
- By rotating the nut a specified amount past the snug-tight condition (Correct answer)
- By applying a calibrated torque measured with a torque wrench
- By heating the bolt and letting it contract
Correct answer: By rotating the nut a specified amount past the snug-tight condition
Turn-of-nut controls tension through a specified nut rotation past snug-tight, often marked with match marks.
Question 105: A contractor needs a specialty excavator for only three weeks on a single project. Which option is usually most economical?
- Purchase used equipment
- Rent the equipment (Correct answer)
- Purchase new equipment
- Lease it for five years
Correct answer: Rent the equipment
For short, infrequent use, renting avoids ownership costs such as depreciation, storage, and financing.
Question 106: When learning new installation techniques & methods in American Institute of Constructors, which approach is MOST effective?
- Combining theoretical study with supervised practical application (Correct answer)
- Learning theory only without hands-on practice
- Observing others without ever performing the techniques
- Practicing without understanding underlying principles
Correct answer: Combining theoretical study with supervised practical application
The combination of theoretical knowledge and supervised practical application provides the deepest understanding and develops competent practitioners.
Question 107: Within how many hours must an employer report a work-related fatality to OSHA?
- 4 hours
- 72 hours
- 24 hours
- 8 hours (Correct answer)
Correct answer: 8 hours
Fatalities must be reported to OSHA within 8 hours of the employer learning of them.
Question 108: Under ASCE 7, what is the typical minimum uniformly distributed live load for office floors?
- 50 psf (Correct answer)
- 100 psf
- 40 psf
- 80 psf
Correct answer: 50 psf
ASCE 7 specifies 50 psf for office floors, with 80 psf for corridors above the first floor.
Question 109: Which NFPA standard covers safeguarding construction, alteration, and demolition operations?
- NFPA 72
- NFPA 25
- NFPA 241 (Correct answer)
- NFPA 80
Correct answer: NFPA 241
NFPA 241 covers fire safety during construction, alteration, and demolition.
Question 110: Under AIA A201, the architect may order which kind of change without the owner's or contractor's agreement?
- Any change below $10,000
- A change to the contract completion date
- A change that adds cost but not time
- A minor change consistent with the intent of the contract documents and with no change in sum or time (Correct answer)
Correct answer: A minor change consistent with the intent of the contract documents and with no change in sum or time
A201 §7.4 authorizes the architect to order minor changes that do not affect the Contract Sum or Time.
Question 111: Under OSHA 1910.178, how often must each powered industrial truck (forklift) operator's performance be evaluated, at minimum?
- Every 5 years
- Every 3 years (Correct answer)
- Only after an accident
- Every year
Correct answer: Every 3 years
Forklift operators must be evaluated at least once every three years.
Question 112: Which barrier MOST commonly hinders effective client communication & service in American Institute of Constructors?
- Over-communicating important information
- Providing too much context for messages
- Lack of active listening and assumptions about understanding (Correct answer)
- Using too many communication channels
Correct answer: Lack of active listening and assumptions about understanding
Failure to actively listen and making assumptions about understanding are the most common barriers to effective communication.
Question 113: When implementing materials & resource management changes in American Institute of Constructors, what factor is MOST critical?
- Speed of implementation regardless of preparation
- Stakeholder buy-in and a clear change management plan (Correct answer)
- Minimizing communication about the changes
- Top-down mandate without input from affected parties
Correct answer: Stakeholder buy-in and a clear change management plan
Stakeholder buy-in and a structured change management plan significantly increase the likelihood of successful implementation.
Question 114: Per ACI 318, what is the minimum concrete cover for reinforcement in concrete cast against and permanently exposed to earth?
- 3 in. (Correct answer)
- 2 in.
- 1-1/2 in.
- 4 in.
Correct answer: 3 in.
ACI 318 requires 3 in. of cover for concrete cast directly against and permanently exposed to earth.
Question 115: When a dispute arises between an AIC member and a client, the preferred ethical approach before pursuing litigation is to:
- Issue a formal notice of claim and cease work pending resolution
- Attempt resolution through negotiation, mediation, or other alternative dispute resolution methods (Correct answer)
- File a mechanic's lien immediately to protect financial interests
- Contact the client's bonding company for direct settlement
Correct answer: Attempt resolution through negotiation, mediation, or other alternative dispute resolution methods
Ethical professional practice favors resolving disputes through negotiation and alternative dispute resolution before resorting to litigation.
Question 116: Resource leveling within available float typically results in which outcome?
- The project end date always gets shorter
- The critical path activities are shortened
- Peaks and valleys in resource demand are smoothed without extending the project (Correct answer)
- Total project cost always increases
Correct answer: Peaks and valleys in resource demand are smoothed without extending the project
Leveling moves non-critical activities within their float to smooth resource use while keeping the completion date.
Question 117: Which standard is used to test and rate through-penetration firestop systems?
- ASTM E84
- ASTM E814 / UL 1479 (Correct answer)
- NFPA 80
- ASTM E119
Correct answer: ASTM E814 / UL 1479
ASTM E814 and UL 1479 test through-penetration firestops and assign F and T ratings.
Question 118: Which test is commonly used to verify the watertightness of a newly installed horizontal waterproofing membrane before it is covered?
- Torque test
- Proctor test
- Flood test (Correct answer)
- Slump test
Correct answer: Flood test
A flood test ponds water on the membrane for a specified period, typically 24-48 hours, to reveal leaks.
Question 119: Using standard 8x16-inch CMU (1.125 blocks per SF of wall), how many blocks are needed for a wall 100 ft long and 10 ft high, before waste?
- 1,250
- 900
- 1,125 (Correct answer)
- 1,000
Correct answer: 1,125
1,000 SF x 1.125 blocks/SF = 1,125 blocks.
Question 120: When a portable ladder is used to access an upper landing, how far must the side rails extend above the landing surface?
- 3 feet (Correct answer)
- 2 feet
- 4 feet
- 1 foot
Correct answer: 3 feet
OSHA 1926.1053 requires ladder side rails to extend at least 3 feet above the upper landing.
Question 121: What is the main purpose of a material expediting log?
- To list approved change orders
- To document safety inspections
- To record worker hours
- To track the procurement status and delivery dates of materials (Correct answer)
Correct answer: To track the procurement status and delivery dates of materials
An expediting log tracks orders, submittals, fabrication, and delivery dates so late materials get flagged early.
Question 122: How often do most U.S. jurisdictions require testable backflow prevention assemblies to be tested?
- Every ten years
- At least annually (Correct answer)
- Only at installation
- Every five years
Correct answer: At least annually
Most water purveyors and plumbing codes require testable backflow assemblies to be tested by a certified tester at least once a year.
Question 123: How many cubic yards of concrete are needed for a slab 60 ft by 40 ft by 6 inches thick, before waste?
- 44.4 CY (Correct answer)
- 88.9 CY
- 400 CY
- 133.3 CY
Correct answer: 44.4 CY
60 x 40 x 0.5 = 1,200 CF, and 1,200 / 27 = 44.4 CY.
Question 124: In American Institute of Constructors, which materials & resource management approach is MOST effective for achieving long-term goals?
- Delegating all decisions without oversight
- Strategic planning with measurable objectives and regular progress reviews (Correct answer)
- Reactive management that addresses issues as they arise
- Focusing solely on short-term financial targets
Correct answer: Strategic planning with measurable objectives and regular progress reviews
Strategic planning with measurable objectives and regular reviews provides direction, accountability, and the ability to adapt strategies based on progress.
Question 125: Which principle underlies the concept of 'responsible bidding' in construction ethics?
- Always submitting the lowest possible bid to win work
- Submitting multiple bids under different company names
- Bidding only on projects for which the constructor is qualified and can perform competently (Correct answer)
- Partnering with other firms to coordinate bid prices
Correct answer: Bidding only on projects for which the constructor is qualified and can perform competently
Responsible bidding requires that constructors only compete for work they have the qualifications, capacity, and resources to perform successfully.
Question 126: When conducting a safety protocols & compliance review in American Institute of Constructors, which approach yields the BEST results?
- Focusing exclusively on equipment checks
- Informal observation without documentation
- Systematic analysis using established frameworks and checklists (Correct answer)
- Reviewing only incidents from the past month
Correct answer: Systematic analysis using established frameworks and checklists
Systematic analysis using established frameworks ensures comprehensive coverage of all potential risks and provides consistent, reliable results.
Question 127: A client asks the contractor for advice that falls within the architect's design responsibility. What is the best response?
- Share constructability input but direct design decisions to the architect of record (Correct answer)
- Redesign the system yourself
- Tell the client the architect is wrong
- Refuse to discuss it
Correct answer: Share constructability input but direct design decisions to the architect of record
Contractors add value through constructability input while respecting the design professional's responsibility and liability.
Question 128: When must a competent person inspect an excavation and its protective systems?
- Only at the start of the project and at substantial completion
- Once per week and after each inspection by OSHA
- Daily before work starts, as needed during the shift, and after rainstorms or other hazard-increasing events (Correct answer)
- Only when the excavation exceeds 20 feet in depth
Correct answer: Daily before work starts, as needed during the shift, and after rainstorms or other hazard-increasing events
1926.651(k) requires daily inspections before work and after any occurrence that could increase hazards, such as rain.
Question 129: What is a liquidated damages clause designed to address in a construction contract?
- Material supply shortages
- Site security expenses
- Project schedule delays (Correct answer)
- Labor disputes
Correct answer: Project schedule delays
A liquidated damages clause in a construction contract specifies a predetermined amount of money that the contractor must pay the owner for each day the project is delayed beyond the agreed-upon completion date. This clause is designed to compensate the owner for losses incurred due to project delays, without the need to prove actual damages in court. It provides a clear financial consequence for failing to meet the schedule.
Question 130: A constructor who provides false information on a project progress report to the owner is violating which fundamental ethical principle?
- Community responsibility
- Honesty and integrity (Correct answer)
- Professional competence
- Sustainability
Correct answer: Honesty and integrity
Providing false information directly violates the core ethical principle of honesty and integrity that underpins all professional relationships.
Question 131: What is the primary purpose of AIA G703?
- Listing schedule-of-values line items and progress for a payment application (Correct answer)
- Releasing liens at final payment
- Documenting a change order
- Certifying substantial completion
Correct answer: Listing schedule-of-values line items and progress for a payment application
G703 is the continuation sheet to the G702 payment application; it details each schedule-of-values line.
Question 132: A project labor agreement (PLA) in construction typically:
- Establishes pre-hire collective bargaining terms for all contractors on a specific project (Correct answer)
- Is required only on projects under $1 million
- Applies only to federal projects in right-to-work states
- Prohibits all union labor on the project
Correct answer: Establishes pre-hire collective bargaining terms for all contractors on a specific project
A PLA is a pre-hire agreement that sets uniform labor terms — wages, hours, dispute resolution — for all contractors working on a specific project.
Question 133: In American Institute of Constructors, which factor MOST influences the selection of appropriate maintenance & repair procedures?
- Personal preference of the practitioner
- The specific requirements and constraints of the situation (Correct answer)
- The most recently developed technique only
- Cost as the sole determining factor
Correct answer: The specific requirements and constraints of the situation
The specific requirements and constraints of each situation should drive technique selection to ensure the most effective and appropriate approach.
Question 134: Under AIA A201, if the Architect rejects work that does not conform to the contract documents, who bears the cost of correcting it?
- The Architect
- The owner
- The building official
- The contractor (Correct answer)
Correct answer: The contractor
The contractor must promptly correct rejected work at its own expense, including added testing and compensation for design services.
Question 135: A construction contractor uses an 'open shop' labor arrangement, which means:
- Workers are not required to be union members as a condition of employment (Correct answer)
- The project is open to the public during construction
- The shop drawings have been approved for construction
- All workers must belong to the applicable trade union
Correct answer: Workers are not required to be union members as a condition of employment
Open shop (merit shop) contractors hire both union and non-union workers, with employment not conditioned on union membership.
Question 136: When a constructor becomes aware that a project's structural design may be deficient, the most ethically appropriate first step is to:
- Stop all work and contact the local building department directly
- Proceed with construction and document the concern in a daily log
- Consult legal counsel before taking any action
- Immediately notify the engineer of record and the owner in writing (Correct answer)
Correct answer: Immediately notify the engineer of record and the owner in writing
Promptly notifying the engineer of record and owner in writing ensures the design professional can evaluate and resolve the concern before it becomes a safety hazard.
Question 137: What is the required height of the top rail of a guardrail system under OSHA 1926.502?
- 36 inches ± 3 inches
- 39 inches ± 3 inches
- 42 inches ± 3 inches (Correct answer)
- 48 inches ± 3 inches
Correct answer: 42 inches ± 3 inches
Top rails must be 42 inches, plus or minus 3 inches, above the walking/working level.
Question 138: Which metric BEST indicates successful materials & resource management in American Institute of Constructors?
- Volume of emails sent
- Number of meetings held per week
- Achievement of defined key performance indicators and stakeholder satisfaction (Correct answer)
- Hours worked by team members
Correct answer: Achievement of defined key performance indicators and stakeholder satisfaction
KPI achievement and stakeholder satisfaction directly measure whether management activities are producing desired outcomes.
Question 139: A Job Hazard Analysis (JHA) is best described as which process?
- Breaking a task into steps, identifying hazards for each, and defining controls (Correct answer)
- A calculation of the company's EMR
- An annual audit of the company safety manual
- A post-incident root cause investigation
Correct answer: Breaking a task into steps, identifying hazards for each, and defining controls
A JHA proactively reviews each step of a job to identify hazards and specify controls before work begins.
Question 140: Purchasing builder's risk insurance to cover potential fire damage during construction is an example of which risk response?
- Mitigation
- Acceptance
- Avoidance
- Transfer (Correct answer)
Correct answer: Transfer
Insurance shifts the financial consequence of a risk to a third party, which is risk transfer.
Question 141: Under A201-2017, how long is the general correction period after substantial completion during which the contractor must correct defective work?
- 6 months
- Two years
- 90 days
- One year (Correct answer)
Correct answer: One year
Section 12.2.2 sets a one-year correction period from substantial completion unless otherwise specified.
Question 142: Under ACI 318, concrete strength is acceptable when the average of any three consecutive tests equals or exceeds f'c and no individual test (for f'c of 5,000 psi or less) falls below f'c by more than how much?
- 250 psi
- 10% of f'c
- 1,000 psi
- 500 psi (Correct answer)
Correct answer: 500 psi
ACI 318 accepts strength when no single test is more than 500 psi below f'c for f'c of 5,000 psi or less.
Question 143: Which document certifies the date when the work is sufficiently complete for the owner to occupy or use it for its intended purpose?
- Final Lien Waiver
- Certificate of Occupancy
- Certificate of Substantial Completion (Correct answer)
- Notice to Proceed
Correct answer: Certificate of Substantial Completion
The Certificate of Substantial Completion (AIA G704) establishes that date and responsibilities for remaining items.
Question 144: In American Institute of Constructors, what is the PRIMARY purpose of conducting regular safety protocols & compliance assessments?
- To identify potential hazards before incidents occur (Correct answer)
- To satisfy insurance requirements only
- To reduce operational costs
- To increase employee workload
Correct answer: To identify potential hazards before incidents occur
Regular safety assessments are primarily conducted to proactively identify and mitigate potential hazards before they lead to incidents or injuries.
Question 145: A curtain wall system has a 20-week fabrication lead time after shop drawing approval. What should the constructor do first to protect the schedule?
- Ask the owner to change to a different system
- Delay the activity until the structure is topped out
- Order the material immediately without approved shop drawings
- Prioritize and expedite the shop drawing submittal and review cycle (Correct answer)
Correct answer: Prioritize and expedite the shop drawing submittal and review cycle
Long-lead items depend on approved submittals, so speeding up the submittal and review cycle protects the delivery date.
Question 146: An owner repeatedly calls the superintendent directly with design change requests. What is the best practice response?
- Ignore the calls entirely
- Courteously route the requests through the formal change process and project manager (Correct answer)
- Implement changes immediately to keep the owner happy
- Charge a fee for each phone call
Correct answer: Courteously route the requests through the formal change process and project manager
Routing changes through the formal process protects scope, cost, and schedule while keeping the client relationship positive.
Question 147: On construction sites, 120-volt, single-phase, 15- and 20-amp receptacle outlets that are not part of permanent wiring must be protected by GFCIs or by what alternative?
- An assured equipment grounding conductor program (Correct answer)
- Arc-flash rated PPE
- Lockout/tagout procedures
- Double-insulated tools only
Correct answer: An assured equipment grounding conductor program
1926.404(b)(1) allows either GFCIs or an assured equipment grounding conductor program for temporary wiring.
Question 148: When crashing a schedule, which activity should normally be shortened first?
- Any activity with a Start-to-Start link
- The critical activity with the longest duration
- The non-critical activity with the most float
- The critical activity with the lowest cost slope (Correct answer)
Correct answer: The critical activity with the lowest cost slope
The most economical approach crashes the critical activity with the lowest cost per day saved first.
Question 149: At what age are concrete cylinders most commonly tested to verify specified compressive strength (f'c)?
- 28 days (Correct answer)
- 7 days
- 3 days
- 90 days
Correct answer: 28 days
Specified compressive strength is typically evaluated at 28 days unless the specs state otherwise.
Question 150: What is the main goal of a formal partnering session at project start?
- To finalize the punch list
- To replace the contract with a handshake
- To negotiate lower subcontractor prices
- To align stakeholders on goals, communication protocols, and issue-resolution processes (Correct answer)
Correct answer: To align stakeholders on goals, communication protocols, and issue-resolution processes
Partnering builds shared goals and an escalation ladder so issues are resolved at the lowest level quickly.
Question 151: In American Institute of Constructors, which factor MOST influences the selection of appropriate installation techniques & methods?
- The most recently developed technique only
- The specific requirements and constraints of the situation (Correct answer)
- Cost as the sole determining factor
- Personal preference of the practitioner
Correct answer: The specific requirements and constraints of the situation
The specific requirements and constraints of each situation should drive technique selection to ensure the most effective and appropriate approach.
Associate Constructor (AC) Exam
This exam certifies entry-level knowledge and skills in construction management, covering fundamental principles and practices.
Exam Rules
- You can skip questions and return to them later
- Flag questions for review before submitting
- No feedback shown until you submit the entire exam
- Unanswered questions count as wrong — answer everything
- 10 pretest questions are mixed in and don't affect your score
- Timer auto-submits when time runs out
- Your progress is auto-saved every 30 seconds
These practice questions were written with AI tools. They are not real exam questions. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy