Kanban Principles and Practices Flashcards
6 cards from real Agile Project Management practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Kanban Principles and Practices flashcards as text
What is the primary purpose of implementing Work in Progress (WIP) limits in a Kanban system?
Answer: To create a pull system and improve the flow of value by preventing bottlenecks.
WIP limits are a core practice of Kanban designed to improve the flow of work. By limiting the number of tasks in any given state, they prevent the system from being overloaded, expose bottlenecks, and force the team to finish work before starting new work. This creates a 'pull system' where new work is only pulled in when there is capacity, leading to a smoother, more predictable delivery of value.
A team observes on their Cumulative Flow Diagram (CFD) that the band for the 'In Progress' stage is widening significantly over time, while the 'Done' band is growing very slowly. What does this pattern most likely indicate?
Answer: Work is arriving into the 'In Progress' stage much faster than it is being completed, indicating a bottleneck.
On a Cumulative Flow Diagram, the vertical width of a band represents the amount of Work in Progress (WIP) for that stage. A widening band for 'In Progress' means that the number of items in that stage is increasing. This happens when the arrival rate into the stage is greater than the departure rate, which is a classic indicator of a bottleneck in the workflow.
Which of the following statements best describes the Kanban principle of 'Start with what you do now'?
Answer: It encourages understanding the current process and respecting existing roles as the initial step for evolutionary change.
This foundational principle emphasizes an evolutionary, non-disruptive approach. Instead of a radical, revolutionary shift, Kanban implementation begins by first understanding and visualizing the current workflow and respecting the existing structure and roles. Improvements are then made incrementally over time.
A Kanban team notices that work items are frequently getting stuck waiting for code review. According to Kanban practices for managing flow, what would be the most effective first action to take?
Answer: Make the entry and exit policies for the 'Code Review' stage explicit and consider applying a specific WIP limit to it.
Kanban's core practices include 'Make Policies Explicit' and 'Limit WIP'. When a bottleneck appears, the first step is to make the process around that stage clear to everyone. Applying a WIP limit to the 'Code Review' column would make the bottleneck's impact visible and encourage the entire team to collaborate on clearing it (e.g., by having developers help with reviews) before pulling new work into the system.
In the context of Kanban flow metrics, what is the key difference between Lead Time and Cycle Time?
Answer: Lead Time is the total time from a customer request to delivery, while Cycle Time is the time from when work actively begins on that request until it is completed.
This is the standard definition used in Kanban. Lead Time represents the entire customer experience, from the moment they make a request to the moment they receive the value. Cycle Time is a subset of Lead Time that measures the internal process efficiency—the time the team is actively working on the item.
Which of the following is NOT a primary goal of implementing feedback loops (Kanban cadences)?
Answer: To compare individual team member performance for annual reviews and compensation.
Kanban feedback loops, such as the daily stand-up, service delivery review, and retrospectives, are designed to improve the system, the process, and the flow of value. Using metrics and discussions from these meetings for individual performance reviews is counterproductive, as it can discourage transparency and create a culture of fear, undermining the goal of collaborative process improvement.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- agilebusiness.org — Eligibility, exam format, passing score, time limit · verified Oct 2026
- apmg-international.com — Fees, renewal, score validity · verified Oct 2026