A product backlog item has been sitting at the top of the backlog for three sprints without being selected. What should the Product Owner do?
-
A
Remove it from the backlog immediately
-
B
Re-evaluate its value, clarify acceptance criteria, and discuss with the team
-
C
Move it to an icebox and never revisit
-
D
Assign it to a developer to be completed outside of sprints