A BA is helping a Scrum team that suffers from 'scope creep within stories' โ developers keep adding features beyond the acceptance criteria. What technique helps prevent this?
-
A
Increase sprint length to accommodate extra features
-
B
Enforce INVEST criteria and clear acceptance criteria as the guardrail
-
C
Remove acceptance criteria to give developers more flexibility
-
D
Let the PO decide during the sprint review what to keep