A new regulatory requirement arrives mid-project that affects 40% of the completed stories. In Scrum, what is the recommended first step?
-
A
Rewrite all completed stories immediately
-
B
Add the regulatory impact items to the Product Backlog and reprioritize with the PO
-
C
Stop all sprints until the regulation is fully analyzed
-
D
Ignore the regulation until the next project