During the Delivery Horizon, stakeholders begin requesting detailed status reports every day. What is the MOST appropriate Agile BA response?
-
A
Produce detailed written reports daily as requested
-
B
Direct stakeholders to the team's information radiators and invite them to sprint reviews for live visibility
-
C
Refuse the request and refer stakeholders to the scrum master
-
D
Schedule weekly formal status meetings instead