During the Delivery Horizon, the BA facilitates a sprint retrospective discussion about requirement misunderstandings. What is the MOST productive outcome?
-
A
Identifying team members responsible for the misunderstandings
-
B
Agreeing on process improvements to how stories are elaborated and accepted going forward
-
C
Documenting the misunderstandings in a formal lessons-learned report for the PMO
-
D
Reducing the number of user stories accepted each sprint