During the Delivery Horizon, a BA notices that a user story's acceptance criteria conflict with a downstream system constraint discovered mid-sprint. What is the BEST immediate action?
-
A
Escalate to the project manager and wait for a decision
-
B
Collaborate with the team and stakeholders to revise the acceptance criteria before the story is coded
-
C
Complete coding based on the original criteria and raise a defect later
-
D
Remove the story from the sprint and reschedule it for the next iteration