A business analyst notices that a stakeholder keeps requesting detailed requirements documents before any development begins. Which Agile principle should the BA use to address this concern?
-
A
Welcome changing requirements, even late in development
-
B
Deliver working software frequently as the primary measure of progress
-
C
Comprehensive documentation over working software
-
D
Follow the plan and avoid scope changes