A business analyst discovers that two stakeholder groups have conflicting priorities for a new feature. What is the FIRST step to resolve this?
-
A
Implement both versions and let users decide
-
B
Understand the underlying needs and business goals driving each group's position
-
C
Defer the feature to a future release
-
D
Ask the product owner to make a unilateral decision