A team is using Kanban. Work items are consistently piling up in the 'In Review' column. What should the business analyst recommend?
-
A
Increase the work-in-progress (WIP) limit for the Review column
-
B
Decrease the WIP limit or add capacity to the review process
-
C
Move items directly to Done to clear the bottleneck
-
D
Split the Review column into multiple sub-columns