How does an agile business analyst handle scope creep during an active sprint?
-
A
Add new items directly into the current sprint
-
B
Document the new request and add it to the product backlog for future prioritization
-
C
Reject all changes until the next release
-
D
Pause the sprint to reassess all requirements