← All CENWAT Flashcard Decks

Pipework Sizing and Installation Flashcards

6 cards from real CENWAT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Pipework Sizing and Installation flashcards as text
  1. What type of fitting is NOT permitted for making joints on gas pipework concealed within walls?

    Answer: Compression fittings

    Compression fittings must NOT be used on gas pipework that is concealed within walls, floors, or where not readily accessible. Only permanent joints such as soldered capillary, brazed, or approved press-fit fittings with gas-specific seals may be used in concealed locations, as compression fittings can loosen over time.

  2. What is the minimum fall required on a condensate pipe from a condensing boiler?

    Answer: A minimum fall of 2.5 degrees, approximately 44mm per metre

    The condensate discharge pipe should have a minimum continuous fall of 2.5 degrees, approximately 44mm per metre run, toward the drain point. The key requirement is a continuous fall with no traps where condensate could collect and freeze.

  3. What is the purpose of a magnetic system filter installed on the return pipe of a central heating system?

    Answer: To capture magnetic iron oxide sludge (magnetite) from the system water

    A magnetic system filter is installed on the return pipe close to the boiler to capture magnetic iron oxide particles (magnetite) from the circulating system water. Magnetite is a product of internal corrosion and if not removed can block the boiler heat exchanger and damage pump seals.

  4. What is the minimum insulation thickness required for central heating pipework in unheated areas under Building Regulations Part L?

    Answer: 19mm for pipes up to 22mm diameter

    Building Regulations Part L requires that central heating pipework in unheated areas such as lofts, garages, and under floors must be insulated. For pipes up to 22mm diameter, the minimum insulation thickness is 19mm with a material having a thermal conductivity of 0.035 W/mK.

  5. When sizing radiators for a room, which heat loss calculation method is commonly used in the UK?

    Answer: Using the U-value method considering fabric heat loss and ventilation heat loss

    The correct method involves calculating total heat loss from the room, including fabric heat loss through walls, windows, floor, and ceiling using U-values, areas, and temperature differences, plus ventilation heat loss based on air changes per hour and room volume. The radiator output must match the total calculated heat loss.

  6. What is the correct procedure for pressure testing a new central heating system before commissioning?

    Answer: Pressurise the system to 1.5 times the maximum working pressure for a minimum test duration, checking for pressure drop

    A new central heating system should be pressure tested at 1.5 times the maximum working pressure, or a minimum of 3 bar for sealed systems, for a defined test period. The system should hold pressure with no detectable drop and all joints should be visually inspected.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. euskills.co.uk — Eligibility, test delivery, exam information · verified Oct 2026
  2. gassaferegister.co.uk — Renewal, score validity · verified Oct 2026