ACCA AK Management Accounting (MA) Standard Costing and Variance Analysis — Questions and Answers
Question 1: What is a standard cost?
- The actual cost incurred during production
- A predetermined cost for a unit of output based on expected conditions (Correct answer)
- The historical average cost calculated over the past year
- The lowest possible cost achievable under perfect conditions
Correct answer: A predetermined cost for a unit of output based on expected conditions
A standard cost is a predetermined cost calculated in advance of production, based on expected levels of efficiency and prices.
Question 2: Which type of standard assumes perfect operating conditions with no wastage or inefficiency?
- Basic standard
- Current standard
- Attainable standard
- Ideal standard (Correct answer)
Correct answer: Ideal standard
Ideal standards assume perfect conditions with no waste, idle time, or inefficiency, making them rarely achievable in practice.
Question 3: The direct material price variance measures the difference between:
- The standard quantity and actual quantity of material used
- The standard price and actual price paid for the actual quantity purchased (Correct answer)
- The budgeted cost and actual cost of materials for budgeted production
- The standard cost and actual cost for the standard quantity
Correct answer: The standard price and actual price paid for the actual quantity purchased
Material price variance = (Standard price – Actual price) × Actual quantity purchased, isolating the effect of price differences on cost.
Question 4: A company has a standard material usage of 5 kg per unit at £3/kg. Actual production was 100 units using 520 kg. What is the material usage variance?
- £60 adverse (Correct answer)
- £60 favourable
- £156 adverse
- £156 favourable
Correct answer: £60 adverse
Standard quantity for actual output = 100 × 5 = 500 kg; variance = (500 – 520) × £3 = £60 adverse.
Question 5: The direct labour rate variance is calculated as:
- (Standard hours – Actual hours) × Standard rate
- (Standard rate – Actual rate) × Actual hours worked (Correct answer)
- (Standard hours – Actual hours) × Actual rate
- (Standard rate – Actual rate) × Standard hours
Correct answer: (Standard rate – Actual rate) × Actual hours worked
Labour rate variance = (Standard rate – Actual rate) × Actual hours worked, measuring the cost impact of paying more or less per hour than standard.
Question 6: If workers complete actual output in fewer hours than the standard allows, the direct labour efficiency variance will be:
- Adverse, as actual hours were less than budgeted hours
- Favourable, as fewer hours were used than the standard allows (Correct answer)
- Nil, because time savings have no monetary effect
- Adverse, because any deviation from standard is unfavourable
Correct answer: Favourable, as fewer hours were used than the standard allows
Labour efficiency variance = (Standard hours – Actual hours) × Standard rate; when actual hours are less than standard hours allowed, the variance is favourable.
Question 7: An adverse variance indicates that:
- Actual performance was better than standard
- The standard was set at an unrealistically high level
- Actual costs were higher or actual revenues were lower than standard (Correct answer)
- The budget was exceeded solely due to uncontrollable external factors
Correct answer: Actual costs were higher or actual revenues were lower than standard
An adverse variance means actual costs exceeded standard costs or actual revenue fell below standard, both of which reduce profit.
Question 8: In a standard costing operating statement, what is the typical starting point?
- Actual profit for the period
- Budgeted profit (or contribution) (Correct answer)
- Standard profit for actual output
- Actual revenue for the period
Correct answer: Budgeted profit (or contribution)
An operating statement starts with budgeted profit, then adds or deducts variances to reconcile to actual profit, bridging planned to actual performance.
Question 9: Which department is typically held responsible for an adverse direct material price variance?
- Production department
- Human resources department
- Purchasing department (Correct answer)
- Finance department
Correct answer: Purchasing department
The purchasing department negotiates and pays for raw materials, making it accountable for paying more or less than the standard price.
Question 10: Which of the following is most likely to cause a favourable direct labour efficiency variance?
- Workers being paid an overtime premium rate
- A general wage rate increase agreed with trade unions
- Workers using a higher-grade material that is easier and faster to process (Correct answer)
- An increase in the purchase price of raw materials
Correct answer: Workers using a higher-grade material that is easier and faster to process
Higher-grade material that is easier to work with reduces processing time, allowing workers to complete output faster than the standard time allows.
Question 11: What does an idle time variance represent?
- The cost of unsold finished goods held in closing inventory
- The cost of hours paid to workers during which no production occurred (Correct answer)
- The difference between budgeted and actual machine downtime charges
- The variance caused by inefficient use of direct materials
Correct answer: The cost of hours paid to workers during which no production occurred
Idle time variance = Idle hours × Standard labour rate, representing wages paid during periods when workers are available but not productively employed.
Question 12: The purpose of splitting variances into planning and operational components is to:
- Eliminate all variances by revising the standard every month to match actuals
- Separate variances caused by poor original planning from those caused by operational performance (Correct answer)
- Allocate responsibility for all variances equally between all departments
- Replace standard costing with activity-based costing in modern businesses
Correct answer: Separate variances caused by poor original planning from those caused by operational performance
Planning variances reflect changes between the original and revised standard due to environmental changes, while operational variances measure actual performance against the revised standard.
Question 13: If actual profit exceeds budgeted profit, what must be true of the net total of all variances for the period?
- The net total of all variances must be adverse
- The net total of all variances must be favourable (Correct answer)
- The net total must be zero as the budget should always balance
- The variances are immaterial and can be ignored
Correct answer: The net total of all variances must be favourable
All variances together bridge budgeted profit to actual profit; if actual profit exceeds the budget, the net effect of all variances must be favourable.
Question 14: A company uses attainable standards. This means the standards:
- Assume perfect efficiency with absolutely no waste or machine downtime
- Are based solely on last year's actual average results without adjustment
- Can be achieved by an efficient and motivated workforce under normal working conditions (Correct answer)
- Remain fixed and unchanged over many accounting periods regardless of changes
Correct answer: Can be achieved by an efficient and motivated workforce under normal working conditions
Attainable standards allow for normal levels of waste and downtime but exclude inefficiency; they are challenging but achievable and are the most commonly used type in practice.