What is the 'Estimate at Completion (EAC)' in EVM and how is a common formula for it calculated?
-
A
EAC projects the final total cost; a common formula is EAC = Actual Cost to Date + (Budget at Completion - Earned Value) / CPI
-
B
EAC is the contractor's bid price adjusted for cost growth to date
-
C
EAC equals the original Budget at Completion plus any contract modifications
-
D
EAC is computed as Planned Value minus Cost Variance