ACAP Cheat Sheet 2026

The 30 highest-yield ACAP facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

100 questions
120 min time limit
70.00% to pass
  1. What discount rate does OMB Circular A-94 prescribe for most federal economic analyses of programs involving real costs and benefits? 7% real discount rate
  2. What does a 'tornado chart' display in cost risk analysis? Ranked sensitivity of total cost to each individual input variable
  3. Which distribution is most commonly used to represent a cost element's uncertainty when only minimum, most likely, and maximum values are known? Triangular distribution
  4. The Word Knowledge - Sample Question Hungry is the opposite of: Full
  5. How many guidelines does ANSI/EIA-748 define for a compliant Earned Value Management System? 32
  6. Under DFARS, which contract types and dollar threshold generally require a contractor to maintain a compliant Earned Value Management System (EVMS)? Cost or incentive contracts with a value of $20 million or more
  7. What does the Variance at Completion (VAC) formula calculate? VAC = BAC - EAC
  8. In cost risk terminology, what is 'aleatory uncertainty'? Irreducible variability inherent to a process or system
  9. Which Army document formally establishes the life cycle cost estimate used to support milestone decision reviews? Program Life Cycle Cost Estimate (PLCCE)
  10. What does Earned Value (EV), also called Budgeted Cost of Work Performed (BCWP), measure? The budgeted amount for the work that has actually been completed
  11. Which type of CSDR report captures recurring and non-recurring costs broken down by cost element and work breakdown structure? Contractor Cost Data Report (CCDR)
  12. Mitigates against the Blast, Penetration, Debris and Cratering effects of warheads VT Fusing or air burst
  13. What is the Performance Measurement Baseline (PMB)? The time-phased budget plan against which project performance is measured
  14. In EVM terminology, what does Planned Value (PV) — also called Budgeted Cost of Work Scheduled (BCWS) — represent? The budgeted cost of work scheduled to be completed by a given date
  15. Which DoD instruction establishes the primary policy framework for the defense acquisition system? DoDI 5000.02 (Operation of the Adaptive Acquisition Framework)
  16. Which Army regulation governs the collection, management, and reporting of cost data for Army acquisition programs? AR 70-13 (Management and Oversight of Defense Acquisition Programs)
  17. What are the four primary cost estimating methodologies recognized in DoD cost analysis? Analogy, parametric, engineering build-up, and expert opinion
  18. The new program was sanctioned by the board of education. You can replace the bold word with: Authorized
  19. Which DoD database is the primary repository for contractor cost and software data collected under CSDR reporting requirements? DACIMS (Defense Automated Cost Information Management System)
  20. Which Estimate at Completion (EAC) formula assumes current cost efficiency will continue for the remainder of the program? EAC = BAC / CPI
  21. What does CSDR stand for in DoD cost data reporting? Cost and Software Data Reporting
  22. What does an amperemeter measure? The current
  23. Mathematics - Sample Question 7.4 x 102 decimeters equal: 7,400 centimeters
  24. What does the Budget at Completion (BAC) represent in an EVM framework? The total authorized budget for the entire program scope
  25. In cost risk analysis, what does 'S-curve' represent? Cumulative probability distribution of cost outcomes
  26. What is the primary purpose of Earned Value Management (EVM) in defense acquisition programs? To integrate cost, schedule, and technical performance measurement
  27. What is the formula for the Schedule Performance Index (SPI)? SPI = EV / PV
  28. Which risk percentile does DoD policy typically require programs to budget to when using probabilistic cost estimates? 80th percentile
  29. In DoD cost risk analysis, what is the 'most likely cost' (MLC)? The mode of the cost probability distribution
  30. In EVM, what is Management Reserve (MR)? Budget withheld from the PMB and held for unplanned but in-scope work
Turn these facts into recall: