What is 'program uncertainty' as distinguished from 'estimating uncertainty' in cost risk analysis?
-
A
Program uncertainty stems from unknown future events; estimating uncertainty stems from imprecision in the cost model itself
-
B
Program uncertainty is always larger than estimating uncertainty
-
C
Program uncertainty applies only to EMD phase programs
-
D
Estimating uncertainty is irreducible while program uncertainty can be managed